برنامج جيت واي (الرواق الشمالي الشرقي) Gateway Program (Northeast Corridor)

هذه مقالة جيدة. لمزيد من المعلومات، اضغط هنا.
(تم التحويل من Gateway Program (Northeast Corridor))

Gateway Program
Construction of a future Gateway Program tunnel portal at West Side Yard in Manhattan
Construction of a future Gateway Program tunnel portal at West Side Yard in Manhattan
استعراض
النوعRail capacity expansion
الوضعUnder Construction
المحطات النهائيةNewark, New Jersey
New York City
الخدماتNortheast Corridor
الموقع الإلكترونيhttp://www.gatewayprogram.org/
التشغيل
المالكAmtrak
السمةUnderground, elevated
تقنية
عرض السكة الحديدية4 ft 8 12 in (1٬435 mm) standard gauge

The Gateway Program is an ongoing expansion and renovation of the Northeast Corridor (NEC) rail line between Newark, New Jersey, and New York City along the right-of-way between Newark Penn Station and New York Penn Station. The project is intended to build new rail bridges in the New Jersey Meadowlands, dig a new set of tunnels under Bergen Hill (Hudson Palisades) and the Hudson River, rehabilitate the existing 1910 tunnel, and construct a new terminal annex. The improvements are designed to double train capacity and permit more high-speed rail service along the current right-of-way, whose two-track rail line, used both by Amtrak and NJ Transit Rail Operations (NJT), has reached its full capacity of 24 trains per hour.[1]

It was unveiled as the Gateway Project in 2011, one year after the cancellation of the somewhat similar Access to the Region's Core (ARC) project; the need for these renovations only increased after Hurricane Sandy had damaged the North River Tunnels the following year.[2][3][4] It took nearly a decade to line up both funding from federal agencies and the state governments involved, and to complete regulatory filings. In 2021, the project was formally approved by the federal government, and work officially began in 2023. The total cost was estimated (in August 2021) to be $16.1 billion. It is scheduled to reach completion by 2035.

Announcement and initial phases

The Gateway Project, as it was originally known, was unveiled on February 7, 2011, by Amtrak President Joseph H. Boardman and New Jersey Senators Frank Lautenberg and Robert Menendez.[5][6][7][8] The announcement also included endorsements from New York Senator Charles Schumer and Amtrak's Board of Directors. Officials said Amtrak would take the lead in seeking financing; a list of potential sources included the states of New York and New Jersey, the City of New York, the Port Authority of New York and New Jersey (PANYNJ), and the Metropolitan Transportation Authority (MTA), as well as private investors.[9][10][11]

By late 2011, two parts of the project were underway: the replacement of the Portal Bridge over the Hackensack River, and the development of Moynihan Train Hall in Manhattan. Environmental impact statements had been completed and the design and engineering of the new bridges had begun.[12][13][14][15][16] The ceremonial groundbreaking of the first phase of the conversion of the James Farley Post Office to the new Moynihan Train Hall took place in October 2010.[17] Some funding for the projects comes from the American Recovery and Reinvestment Act of 2009.[18][19][20][21]


Background

Right-of-way

New York Tunnel Extension, 1912

The right-of-way was originally developed by the Pennsylvania Railroad (PRR)[22] in conjunction with the 1910 opening of New York's Pennsylvania Station, which required the construction of the Portal Bridge over the Hackensack River, as well as the North River Tunnels under the Hudson Palisades and Hudson River.[23]:37, 39 The following year the Manhattan Transfer station was opened in the Kearny Meadows to allow changes between steam and electric locomotives. This station also provided for passenger transfers to/from its former main terminal at Exchange Place in Jersey City or the Hudson and Manhattan Railroad (H&M), the forerunner of today's Port Authority Trans Hudson (PATH).[23]:41–42 The Dock Bridge over the Passaic River was opened in conjunction with the adjacent Newark Penn Station in 1935.[24][25] In 1937, the H&M was extended over a second span, making the transfer in the meadows redundant.[26]

In 1949, the PRR discontinued its ferry system on the Hudson, and in 1961, it closed its Exchange Place station.[27] In 1963, due to declining traffic and revenue, the PRR demolished the above-ground New York Penn Station. It retained its below-ground passenger concourses and waiting areas, and sold its air rights, enabling construction of a new Madison Square Garden.[28] In 1967, the Aldene Plan was implemented, requiring the floundering Central Railroad of New Jersey (CNJ), Reading (RDG), and Lehigh Valley (LV) railroads, to travel into Newark Penn while continuing service to New York Penn.[23]:61[29] Under continued financial pressure, the PRR merged with New York Central (NYC) in 1968, but the newly-formed Penn Central (PC) declared bankruptcy on June 21, 1970. In 1976, the PC long-distance service (including part of today's Northeast Corridor and Empire Corridor) was assumed by Amtrak, which had been founded in 1971.[30] Conrail was created in 1976 to consolidate numerous Northeast private railroads, including commuter service on the CNJ and the LV.[31][32] Conrail divested itself from passenger operations in 1983, and NJT assumed control.[33]

In 1991, NJT opened the Waterfront Connection, extending service on several non-electrified trains which had previously terminated at Newark Penn Station to Hoboken.[34] In 1996, NJT inaugurated Midtown Direct service, rerouting some trains from the west which previously terminated at Hoboken Terminal to New York Penn.[35][36] Secaucus Junction was opened in 2003, allowing passengers travelling from the north to transfer to Northeast Corridor Line, North Jersey Coast Line, or Midtown Direct trains, though not to Amtrak, which made no stops there. Between 1976 and 2010, the number of NJT weekday trains crossing the Hudson using the North River Tunnels (under contract with Amtrak[37]) increased from 147 to 438.[7]

Trans-Hudson crossings

The Northeast Corridor is the most heavily traveled railway in the United States, and is the only rail line that travels under the Hudson River and through New York City.[38] The other rail system crossing the Hudson was developed by the Hudson and Manhattan Railroad, partially in conjunction with the PRR,[39] and taken over by PANYNJ in 1962, who rebranded the H&M as the PATH, a rapid transit system.[40] Direct trans-Hudson rail service to Lower Manhattan from Newark Penn is provided by PATH with additional terminals at World Trade Center and Herald Square in Manhattan, and at Hoboken Terminal and Journal Square in Hudson County, New Jersey.[41] In 1971 New Jersey Governor William T. Cahill proposed constructing another rail tunnel from Weehawken, New Jersey, to 48th Street in Midtown Manhattan.[42]

There are three vehicular crossings of the lower Hudson River.[43] The Holland Tunnel, opened in 1927, is minimally used for public transportation and connects Jersey City, New Jersey, to lower Manhattan. The George Washington Bridge, opened in 1931, is used by suburban buses to GWB Bus Terminal, and connects Fort Lee, New Jersey, to upper Manhattan. Its lower level, opened in 1962, is the last new river crossing.[44] The Lincoln Tunnel, composed of three tubes opened in 1937, 1945, and 1954, connects Weehawken, New Jersey, to Midtown Manhattan.[45] More than 6,000 bus trips are made through the tunnel and bus terminal daily.[46] Its eastern terminus is connected via ramps to the Port Authority Bus Terminal, the gateway for most NJT bus traffic entering Manhattan.[47] Despite the Lincoln Tunnel XBL (express bus lane) during the morning peak there are often long delays due to traffic congestion and the limited capacity of the bus terminal.[48][49][50]

Access to the Region's Core

Site of the western portal of the tunnel in North Bergen at Tonnelle Avenue

Launched in 1995 by PANYNJ, NJT, and MTA, Access to the Region's Core (ARC) was a Major Investment Study that looked at public transportation ideas for the New York metropolitan area. It found that long-term goals would best be met by better connections to and in-between the region's major rail stations in Midtown Manhattan, Penn Station and Grand Central Terminal.[51] The East Side Access project, including tunnels under the East River and the East Side of Manhattan, was completed in early 2023; some LIRR traffic has been diverted to Grand Central, freeing up track slots at Penn Station.[52][53][54]

The Trans-Hudson Express Tunnel or THE Tunnel, which later took on the name of the study itself, was meant to address the western, or Hudson River, crossing. Engineering studies determined that structural interferences made a new terminal connected to Grand Central or the current Penn Station unfeasible and its final design involved boring under the current rail yard to a new deep cavern terminal station under 34th Street.[55][56] While Amtrak had acknowledged that the region represented a bottleneck in the national system and had originally planned to complete work by 2040,[57] its timetable for beginning the project was advanced in part due to the cancellation of ARC, a project similar in scope, but with differences in design.[58] That project, which did not include direct Amtrak participation,[57][59] was cancelled in October 2010 by New Jersey governor Chris Christie, who cited potential cost overruns.[60] Amtrak briefly engaged the governor in attempt to revive the ARC Tunnel and use preliminary work done for it, but those negotiations soon broke down.[10][57][59] Amtrak said it was not interested in purchasing any of the work.[61] Senator Menendez later said some preparatory work done for ARC may be used for the new project.[62] Costs for the project were $117 million for preliminary engineering, $126 million for final design, $15 million for construction and $178 million real estate property rights ($28 million in New Jersey and $150 million in New York City). Additionally, a $161 million partially refundable pre-payment of insurance premiums was also made.[63]

Funding and start of construction

Projected costs

In 2011, the project was projected to cost $13.5 billion and finish in 2020. In April 2011, Amtrak asked that $1.3 billion in United States Department of Transportation funding for NEC rail corridor improvements be allocated to Gateway and related projects.[64][65] In November, Congress allocated $15 million for initial engineering work.[66][67][68]

In 2012, revised projections put the cost at $14.5 billion and completion date at 2025.[69] In April 2012, the a U.S. Senate subcommittee proposed another $20 million.[70][71] In September 2012, Schumer estimated that the project would need $20 million in 2013 and $100 million in 2014 to keep it from dying.[72]

In December 2012, Amtrak requested $276 million from Congress to upgrade infrastructure damaged by Hurricane Sandy that would also eventually support trains run along the new Gateway Project right-of-way.[73][74][75] That earmark funding, which had been revised to $188 million, was deleted from the legislation.[76] However, the United States Department of Transportation provided $185 million from its portion of these Sandy relief and resiliency funds to build the "tunnel box" under the Hudson Yards redevelopment project and rebuild an overlapping Maintenance of Equipment building for the Long Island Rail Road.[77]

In July 2017, the projected cost for the new tunnels under the Hudson River and for the repair of the North River Tunnels increased to $12.9 billion, up from a previous estimate of $7 to 10 billion.[4][78][79]:S-10

In August 2021, projected costs for construction of the new tunnels and repair of the existing North River Tunnels was revised to $12.3 billion in a financial plan submitted on behalf of the Gateway Development Commission.[80][81] The States of New York and New Jersey identified their sources of funding for the project, and Amtrak increased its contribution to the project. Early in 2022, the FTA upgraded the rating for the sought Federal Grant share of the tunnel to project, making it eligible for funding.[82] In July 2022, the governors of New York and New Jersey signed a memorandum in which the two states' governments agreed to share the cost of the project.[83][84] By that August, the projected cost of the tunnels and related projects had increased to $16.1 billion.[85][86]


Development corporation and commission

In November 2015, the creation of the Gateway Development Corporation was announced by Amtrak, U.S. Senators Cory Booker and Chuck Schumer, and Governors Christie and Cuomo.[87][88] The corporation oversaw planning, environmental, design, engineering, and construction work, and it also sought federal grants and applied for loans. Its board was composed of Port Authority of New York and New Jersey board members, the USDOT, and Amtrak, while its staff consisted of PANYNJ and Amtrak employees.[89][90]

In December 2015, federal legislation was introduced to allow Amtrak to operate the NEC as a financially separate entity that could invest profits from the line into its infrastructure. The legislation also provided for more low-interest loans through changes in the Railroad Rehabilitation and Improvement Financing and Capital Investment Grant (New Starts) federal funding programs.[91] In March 2016, Amtrak and PANYNJ committed $35 million each for design and engineering work.[92] Additional funding has not been identified.[93]

The group met for the first time on January 12, 2017.[94][95] On June 30, 2017, the U.S. Department of Transportation sent a letter to the Gateway Development Corporation permanently withdrawing from its board of trustees.[96] Shortly afterward, the draft Environmental Impact Study for the project was issued.[4]

By 2019, project stakeholders had decided to create a bi-state agency to oversee the project's planning, funding, and construction of the rail tunnels and bridges. Creating this Gateway Development Commission required identical legislation in the New York and New Jersey legislatures, which both states passed on June 24, 2019.[97][98] The law sets standards for transparency and accountability, and says that each state is responsible for half the funding. The Commission can receive funds from federal, state, and local sources.[99] The Commission's first CEO, Kris Kolluri, was nominated by New York governor Kathy Hochul and New Jersey governor Phil Murphy in early 2022.[100][101] Kolluri resigned July 18, 2024, one month after he was repeatedly mentioned in the indictment of powerful South Jersey political boss George Norcross.[102]

Blocked by Trump administration

The administration of President Barack Obama called Gateway the most vital piece of infrastructure that needs to be built in the United States.[103] Port Authority of New York and New Jersey Chairman John J. Degnan said in May 2015 that the agency "would step up to the plate" with regard to funding the project,[104][105] and in a September 2015 joint letter to Obama, New Jersey Governor Chris Christie and New York Governor Andrew Cuomo offered to pay half of the project's cost if the federal government picked up the rest.[106][107][108] After President Donald Trump took office, however, his administration began to cast doubt on funding the project, as Trump suggested defunding the Federal Transit Administrations (FTA)'s New Starts program for all new projects,[109] despite his own Secretary of Transportation Elaine Chao calling the project "an absolute priority".[110]

In September 2017, $900 million was allocated for the project in a House of Representatives spending bill,[111] but under pressure from Trump, 155 Republican and four Democratic representatives co-sponsored a proposed amendment to remove the funding, with North Carolina Republican Ted Budd saying, "North Carolina and the other 48 states should not have to foot the bill for this hall of fame earmark."[112][113] A bipartisan group of representatives from New Jersey disagreed, with Republican Rodney Frelinghuysen saying, "The people of Texas, victims of an historic storm (Hurricane Harvey), need additional federal disaster assistance. The people of New Jersey need a safe and well-functioning transportation infrastructure. I intend to continue to fight for both."[112][113]

On December 14, 2017, Governor Chris Christie committed $1.9 billion, New Jersey's share of the tunnel cost.[114] On December 29, 2017, multiple news sources published a letter from a Trump administration FTA official who stated that the Gateway Program was a "local" project, putting federal funding for the project in doubt.[115][116]

In March 2018, Trump directly pressured Republican House Speaker Paul Ryan to oppose federal funding for the Gateway Program in the omnibus spending bill that was then being worked on.[117][113] When the Consolidated Appropriations Act was signed on March 23, 2018, it provided $2.9 billion to discretionary grant programs,[118][119] which Democrats said could provide as much as $541 million for Gateway,[120] with $388 million coming from $650 million for improvements to the Northeast Corridor and another $153 million coming from FTA grants.[119][121]

In June 2018, the State of New Jersey approved $600 million in bonds to finance the Portal Bridge part of the project.[122][123][124] In its 2020 budget, the Trump administration again proposed cutting funding for the Gateway Program by half, from $650 to $325 million.[125][126][127]

Approval and funding under Biden

With the inauguration of Joe Biden as U.S. President in January 2021, discussion resumed on funding the Gateway Program. Schumer, who had become the Senate majority leader, said that month he was working with Biden administration Transportation Secretary Pete Buttigieg to allocate $12 billion to the project.[128][129] Buttigieg supported the project, saying, "This is a regional issue, but one of national significance."[130]

On May 28, 2021, the project was formally approved by the federal government.[131][132][133] The Infrastructure Investment and Jobs Act, passed in November 2021, appropriated billions for projects like Gateway and other upgrades to the Northeast Corridor.[134] The next month, the United States Army Corps of Engineers gave final approval.[135][136] On August 31, 2022, the Gateway Development Commission announced the new tunnels would be completed in 2035 and the existing North River Tunnels would be rehabilitated by 2038.[85][137]

In July 2022, New Jersey and New York officials each agreed to pay 25 percent of the project's cost; under the agreement, federal officials would pay 50 percent.[138][139] The New Jersey Turnpike Authority agreed to help fund New Jersey's portion of the project in December 2022.[140][141] Schumer said the same month that construction on the project would commence in 2023 with $292 million in federal funding,[142] which Biden announced would be used to complete the Hudson Yards "tunnel box".[143][144] In July 2023, the FTA promised a $6.88 billion grant, the largest transit grant that the federal government had ever given;[145][146] the grant was finalized the following June[147][148] and handed over to the Gateway Development Corporation that July.[149][150] Another $3.8 billion grant was provided in November 2023.[151][152] All told, $12 billion in federal funding for the $16 billion project was planned to be committed by the 2024 United States presidential election, bringing the project to a "point of no return".[153][154]

The new tunnel is scheduled to open in 2035.[155]

Governance

اعتبارا من July 2023, the board consists of:[156]

  • New Jersey Co-Chair – Balpreet Grewal-Virk – Appointed by Phil Murphy
  • New York Co-Chair – Alicia Glen – Appointed by Kathy Hochul
  • Amtrak Vice Chair – Tony Coscia
  • New Jersey Commissioner – Janine Bauer – Appointed by Phil Murphy
  • New Jersey Commissioner – Amy Rosen – Appointed by Phil Murphy
  • New York Commissioner – Jamey Barbas – Appointed by Andrew Cuomo
  • New York Commissioner – Marie Therese Dominguez – Appointed by Andrew Cuomo

اعتبارا من July 2023, the Executive Director was Kris Kolluri, who resigned in July 2024.[102] He was succeeded in 2025 by Thomas F. Prendergast.[157][158]

Project components

The current route, about 11 miles (18 km) long, includes infrastructure that was built in the 1900s and 1910s.[159] The system operates at capacity during peak hours—24 trains per hour—and limits speed for safety reasons.[160] The new route would run parallel to the current right-of-way, enabling dispatching alternatives, potential speed increases, and up to 24 more trains per hour.[1]

Newark Penn, Dock Bridge, and Harrison PATH station

NEC passes through Harrison Station.

Six tracks connect Newark Penn Station and the adjacent Dock Bridge over the Passaic River at 40°44′05″N 74°9′51″W / 40.73472°N 74.16417°W / 40.73472; -74.16417. The station and the west span of the bridge, carrying three tracks, were built in 1935. The east span, opened in 1937, carries one outbound track and the two Port Authority Trans Hudson (PATH) rapid transit tracks. To the northeast lies the PATH's Harrison station. From the bridge and through the station, Amtrak and NJT trains run on three center tracks; the PATH uses side platforms. Maps for the Gateway Program indicate that a fourth track for the NEC will be added through the station.[7]

The bridge, owned by the Port Authority of New York and New Jersey (PANYNJ), was repaired in 2009.[161]

In the 2010s, the station received a $173 million reconstruction and expansion. Unrelated to the Gateway Program, it was funded by the PANYNJ, which owns and operates the PATH, and the Federal Transit Administration.[162]


Sawtooth Bridges-Kearny Meadows

Amtrak Bridge 7.80 crossing over NJTransit

At the Sawtooth Bridges at 40°44′38″N 74°7′30″W / 40.74389°N 74.12500°W / 40.74389; -74.12500[163] east of the former Manhattan Transfer, the rights-of-way of Amtrak, and PATH, and several NJT lines converge and run parallel to each other. While there is no junction with PATH, NJT trains can switch tracks, depending on their terminal of origination or destination, enabling Midtown Direct trains on the Morris and Essex Lines to join or depart the Northeast Corridor.[35][36] The single track limited-use Waterfront Connection connects some lines using diesel trains on Hoboken Terminal trips with the NEC to the west.[34] Plans call for replacement of the bridges and expansion from two to four tracks, requiring the construction of bridges in the Kearny Meadows at Newark Turnpike and Belleville Turnpike.[7]

Portal Bridge

The Portal Bridge is a major pinch point of the Northeast Corridor, as problems closing the bridge cause delays for thousands of rail commuters.
The right-of-way would parallel the NEC and pass through Secaucus Junction

The subproject Portal Bridge Replacement would construct two new two-track rail bridges over the Hackensack River, replacing the existing Portal Bridge built in 1910: the Portal North Bridge and the Portal South Bridge.[7]

The old Portal Bridge at 40°45′13″N 74°5′41″W / 40.75361°N 74.09472°W / 40.75361; -74.09472 (Portal Bridge) is a two-track, rail-only, 961-foot (293 m) swing bridge over the Hackensack River between Kearny and Secaucus. Its design limits train speeds, temporarily prohibits crossings when open, and requires frequent and costly maintenance.[13][164] Its lowest beams are 23 feet (7.0 m) above the water, so it opens regularly for shipping,[164] though not during weekday rush hours, when trains have priority.[165] In addition to the drawbacks that come with the swing bridge design itself, due to its substantial age and bad state of repair the Portal Bridge frequently failed to close properly after swinging back, causing major disruptions for riders on NJ Transit and Amtrak.[166]

The first phase of the project is the construction of the two-track Portal North Bridge, expected to take 6 years to complete once construction begins. The Portal North Bridge would replace the tracks on the existing Portal Bridge one-by-one. It would hence yield reliability improvements, but not increase capacity.[167] After the Portal North Bridge enters service, the old Portal Bridge would be demolished. A twin bridge, the Portal South Bridge, would eventually double the number of tracks to four, thus matching the rest of the Northeast Corridor.[168]

Construction on the Portal North bridge began on August 1, 2022, with a groundbreaking ceremony.[169] The Portal North Bridge was halfway complete and on budget by mid-May 2024.[170] In November 2024, the first of three arch segments was floated to the construction side, after being assembled off-site.[171] As of November 2024, no funding commitment has been made for the two-track Portal South Bridge, leaving its timeline uncertain.

In December 2008, the Federal Railroad Administration (FRA) approved a $1.34 billion project to replace the Portal Bridge with two new bridges: a three-track bridge to the north, and a two-track bridge to the south.[13] In 2009, New Jersey applied for funding from the American Recovery and Reinvestment Act of 2009 and on January 28, 2010, received $38.5 million for design.[172] In April 2011, Amtrak applied for $570 million for construction from US DOT. New Jersey was expected to contribute $150 million.[65]

In the early design years, cycling advocates, with Lautenberg's support, lobbied to include a bike path that would have become part of the East Coast Greenway, however that was not included in the final design of the Portal North Bridge.[15][173]

In October 2015, a $16 million TIGER grant was awarded and will be used to support early construction activities such as realignment of a 138 kV transmission monopole, constructing a temporary fiber optic cable pole line, building a finger pier construction access structure, a service access road and a 560-foot retaining wall.[174][175]

Construction on the new bridges had been scheduled to begin in 2010 and wrap up in 2017, at which time the Portal Bridge would have been dismantled; however, the project encountered numerous delays primarily due to a lack of state and federal funding during the Republican administrations of New Jersey Governor, Chris Christie and U.S. President Donald Trump, both of whom opposed the project.[6][7][12][13][58][176]

In June 2020, Trump informed NJ Governor Phil Murphy that he would no longer oppose the Portal Bridge replacement, allowing the project to begin once it could be properly financed.[177]

Secaucus Junction–Bergen Loop

Opened on December 15, 2003, at a cost of $450 million, Secaucus Junction (at 40°45′42″N 74°04′30″W / 40.76161°N 74.074985°W / 40.76161; -74.074985) is an interchange station served by nine of New Jersey Transit's rail lines, and is sited where Hoboken Terminal trains intersect with those traveling along the Northeast Corridor. Passenger transfers are possible, but there is no rail junction. While Access to the Region's Core had planned a loop to create a junction,[178] original plans for the Gateway Program did not. Amtrak trains pass through the station, but do not stop there, nor are there plans to include an Amtrak stop.[7] In April 2012, Amtrak announced that the project might include a "Bergen Loop" connecting Main Line, Bergen County Line, Pascack Valley Line and Port Jervis Line service[179] to the NEC at Secaucus Junction.[180][181] MTA constituencies are encouraging the agency to include funding for the loop its capital plan.[182]

If a loop were built, passengers bound for New York Penn Station would not need to use Secaucus Junction for transfers. Trains using the loop would also increase the capacity demands on the already over-capacity NEC which the Gateway Program is designed to alleviate. Suburban property owners along the Main Line/Bergen County Line and Pascack Valley Line would stand to gain economically as property values have increased significantly along commuter rail lines once they were upgraded to offer "single-seat commutes".[183]

Tunnels

The Gateway Tunnel will join the current right-of-way at the south side (left.)

The Gateway Program would build two new tunnels, doubling the rail capacity.[79]:S-2 to S-3, S-10[184]:5B-17 The current North River Tunnels allow a maximum of 24 one-way crossings per hour;[160][185] the Gateway proposal would allow an additional 24 trains per hour.[1]

North River Tunnels

The North River Tunnels were 102 years old when they were inundated by seawater from Hurricane Sandy in October 2012.[186] If the new Hudson Tunnel is not built, the North River Tunnels will have to be closed one at a time, reducing weekday service below the existing level of 24 trains per hour. Due to the need to provide two-way service on a single track, service would be reduced by over 50 percent.[185] In the best-case scenario, with perfect operating conditions, 9 trains per hour could be provided through the tunnel, or a 63% reduction in service. During the duration of construction, passengers would have to use overcrowded PATH, buses, and ferries to get between New Jersey and New York.[187]:1–7 In May 2014, Amtrak CEO Joseph Boardman told the Regional Plan Association that there was something less than 20 years before one or both of the tunnels would have to be shut down.[188]

As a result of the storm damage and the tunnels' age, component failures regularly occur within the tubes, resulting in frequent delays.[2] One report in 2019 estimated that the North River Tubes and the Portal Bridge contributed to 2,000 hours of delays between 2014 and 2018.[189] The North River Tunnels need to be repaired without major reductions in weekday service, making it necessary to have new tunnels built. Once the new tunnels open, the two North River Tunnels would close for repairs, one at a time, with the existing level of service maintained. This is because the new tunnel would be located further south–there would be no access to Track 19, and Tracks 9–18 would only have access to the tunnel by the single I ladder-track. Once the new North River Tunnels reopen in 2030, capacity on the line would be doubled. The Hudson Tunnel Project would also allow for resiliency on the Northeast Corridor to be increased, making service along the line more reliable with redundant capacity.[79]:S-2 to S-3, S-10[184]:5B-17

Hudson Tunnel

The Gateway Hudson River tunnel, one point of which would be at 40°45′17″N 74°01′00″W / 40.75479°N 74.01677°W / 40.75479; -74.01677, will travel from a point at Weehawken Cove under the Hudson River and its eastern portal south of West Side Yard in Manhattan.[7] Engineering studies for ARC along this route had been deemed unfeasible.[190] Surveys of properties which would or would not be affected by underground construction at underground eastern end of the ARC Tunnel had been completed.[191]

In April 2011, $188 million in federal funding was requested for preliminary engineering studies and environmental analysis.[65][192] On May 2, 2016, the FRA published a Notice of Intent to jointly prepare an environmental impact statement (EIS) with NJ Transit for the Hudson Tunnel Project under the National Environmental Policy Act (NEPA). The EIS will evaluate the potential environmental impacts of a reasonable range of alternatives, including a no-build alternative. As appropriate, FRA and NJ Transit will coordinate with Amtrak and PANYNJ on the EIS.[193]

The ARC Tunnel was to be built in three sections: under the Hudson Palisades, under the Hudson River, and under the streets of Manhattan, where it would have dead-ended. The Hudson Tunnel will likely be built along the footprint of the Palisades and river sections, but will enable trains to join the current interlocking once it emerges. A flying junction is planned for later stages. This will allow Amtrak and NJT to continue to use the East River Tunnels and Sunnyside Yards for staging, storage, and carrying Amtrak NEC trains.[7] The Draft Environmental Impact Study (DEIS) for Gateway tunnels was issued in June 2017. Four alternatives for alignments under the Hudson River and the Palisades. Option 1 would have the new tunnels run close to the existing tunnels with a ventilation site near the Lincoln Tunnel Helix. This option would have required a construction staging site within the Lincoln Tunnel Helix, thus displacing New Jersey Transit's Weehawken bus storage site, which would have a negative impact on the operation of buses to the Port Authority Bus Terminal. Option 2 would have the new tunnels run further south than the first option, with a shaft site north of 19th Street near JFK Boulevard East. This option would require the acquisition and demolition of an existing multi-story office building to build the shaft site. The third option would be further south with a shaft site south of 19th Street. This option would preclude the development of a portion of a planned residential development under construction at 800 Harbor Boulevard. The fourth option would be further south with a shaft site south of 18th Street, following the same horizontal alignment identified in the ARC FEIS. Alignment Option 4 was chosen for the build alternative even though it would have a slightly longer tunnel than in the other alternatives. Because of the additional length, there would be additional tunneling costs for this option. The first three options have greater pre-construction risks, meaning that if construction was delayed the cost difference would be minimized. In addition, Option 4 does not have the issues that the first three options have.[79]:S-6[187]:2–9 to 2–10

The new tunnel would be built to comply with the National Fire Protection Association (NFPA) 130, Standard for Fixed Guideway Transit and Passenger Rail Systems, with the two tubes connected by cross passages every 750 feet (230 m) with fire-rated doors to separate the two tubes.:S-9[79] The tunnel would be constructed through the use of two tunnel boring machines beneath the river bottom.[79]:S-11

While the Hudson Tunnel Project would double the number of tracks under the Hudson River, it would not result in an increase in rail capacity due to constraints at Penn Station. Penn Station operates at capacity during peak periods, and since it takes a long time for passengers to board and alight trains, trains cannot leave and enter the station as might otherwise be possible. Even with improvements in the station, there are inadequate train storage facilities at Penn, and there is no capacity in the East River Tunnels to allow for trains to be stored during middays at Sunnyside Yard. Without these additional improvements, it is assumed that the same number of trains going between New Jersey and New York today would be operating in 2030, albeit with the additional tunnel capacity.[79]:S-9 to S-10 The first construction contract relating to the tunnel itself, a contract for stabilizing the riverbed, was awarded in February 2024.[194][195] By mid-2024, the first tunnel boring machine was scheduled to begin digging in late 2024 or early 2025, while a second TBM was to begin digging in 2026. Each TBM was expected to take two years to finish excavating its respective tube.[196]

Palisades Tunnel

A groundbreaking for ARC was held on June 8, 2009,[197] for new underpass at 40°45′56″N 74°2′14″W / 40.76556°N 74.03722°W / 40.76556; -74.03722 (Gateway Palisades Tunnel), under Tonnelle Avenue in North Bergen near the site western portal of the tunnel through Hudson Palisades just south of the North River Tunnels. The land, which cost $26.3 million, is owned by NJT.[198] A tunneling contract for the Palisades Tunnel was awarded on May 5, 2010, to Skanska.[199][200] Maps indicate this part of the Hudson Tunnel would follow a route to the Weehawken-Hoboken border.[7] In October 2012, in an eminent domain case for a property in Weehawken NJ Transit acquired a parcel in the path of the tunnel for $8.5 million.[201] Federal funding of $25 million for the completion of an overpass carrying U.S. Route 1/9 above the New Jersey portal was authorized in June 2023,[202] and the Gateway Development Commission awarded $47.3 million in contracts that September to raise Tonnelle Avenue above the portal.[203][204] Work on the Tonnelle Avenue overpass began in November 2023.[205]

Hudson Yards "tunnel box" and West Side Yard

A "tunnel box" was built in the West Side Yard to preserve a right-of-way for future use.

The air rights over the West Side Yard are being developed as a residential and commercial district on a platform constructed over the yard as part of the Hudson Yards project.[206][207] Placing a new Amtrak portal in Manhattan could have conflicted with the Hudson Yards project, which broke ground in late 2012.[72] In February 2013, Amtrak officials said they would commission a project to preserve a right-of-way under Hudson Yards for future use, to be built with $120 million to $150 million in federal funds.[208][209][210] in June 2013 it was announced that $183 million had been dedicated to the "tunnel box" as part of Hurricane Sandy recovery funding.[211][212][213]

Construction began on the first phase, from 10th Avenue and 11th Avenue between 31st Street and 33rd Streets, on September 23, 2013, at 40°45′17″N 74°00′14″W / 40.754661°N 74.003783°W / 40.754661; -74.003783.[214] The underground concrete casing for the first phase was 800 ft (240 m) long, 50 ft (15 m) wide, and about 35 ft (11 m) tall.[215] Amtrak awarded Tutor Perini a $133 million contract to build a section of box tunnel.[216] This portion was completed a year later. Amtrak, NJ Transit, and the MTA applied to the Federal Transit Administration for a $65 million matching grant for another 105 ft (32 m) long structure to preserve the right-of-way at 11th Avenue in Manhattan[217][218] under a viaduct that was rehabilitated in 2009–2011.[219][220] Construction started in December 2014 and was nearing completion اعتبارا من July 2017, though funding disputes stalled the tunnel box's completion.[221] The tunnel box was substantially complete by November 2017.[222] The following phase would extend the casing between 11th and 12th Avenue as the development of Hudson Yards continues westward.[223] Work on the concrete tunnel box resumed in November 2023.[151][224]

To connect the tunnel to Penn Station, extensive track modifications will be required. The profile of several tracks will have to be lowered so that they can meet the grade of the new tunnel tracks at the new portal within A Yard. The I Ladder track, which runs diagonal to the other tracks to provide connections to the platforms tracks, would be extended to connect to the new tracks from the tunnel, allowing trains to stop on Tracks 1 through 18. Some tracks within A Yard would be reconfigured. While construction takes place in A Yard, the three trains stored in A Yard and D Yard would be stored in other locations due to the unavailability of storage tracks in those yards. The Empire Line tunnel, near Tenth Avenue, will be modified: 100 feet of that tunnel beneath Tenth Avenue will be lowered so its tracks can connect to the lower track profile in A Yard. This work will be done during weekends over a 20-month period, or through a full closure of the Empire Line tunnel for two to three months. All of this work would take 21 months.[184]:5B-15 to 5B-16

New York Penn Station

Penn Station, the 1968 structure that replaced the original Pennsylvania Station in New York, has been called the "busiest, most congested, passenger transportation facility in North America on a daily basis".[225] It is used by Amtrak, New Jersey Transit, and the Long Island Rail Road (LIRR), and served by several New York City Subway lines. Between 1976 and 2010 weekday train movements increased 89%, from 661 to 1,248, reaching what is considered to be capacity.[7] In 2010, the station saw 550,000 daily boardings/alightings.[11][226][227]

Penn Station is part of the Pennsylvania Plaza complex that includes Madison Square Garden (MSG).[28] In 2013, the New York City Council voted to extend the MSG Special Permit by up to ten years, in an effort to have the arena move to a different location so that a new station structure can be built in its place.[228][229][230]

Moynihan Train Hall

NEC passes under the James Farley Post Office, as seen looking southeast at the rear of the building.

In the early 1990s, then-New York Senator Daniel Moynihan championed a proposal to convert the James Farley Post Office to a train station.[226][231] Opened in 1912, soon after the original Pennsylvania Station, the landmark building stood across from Penn Plaza and was built over tracks approaching the station from the west.[232][233]

In 2010, work began on a $267 million Phase 1. This phase consisted of an expansion of the Long Island Rail Road's underground West End Concourse, which ran under the Farley Building's main entrance, as well as two entrances to the existing Penn Station platforms through the Farley Building on Eighth Avenue.[234][235][236] A groundbreaking ceremony took place on October 18, 2010.[237][238][239] In May 2012, the PANYNJ announced that a $270 million contract for the first phase, including the concourse expansion under 8th Avenue, had been awarded.[240][241] The West End Concourse opened in June 2017.[242][243][244]

Phase 2 consisted of the new train hall in the fully renovated Farley Building. In January 2016, New York governor Cuomo announced plans for a combined Penn-Farley Post Office complex, a project estimated to cost $3 billion.[245][246] At that time, the project was renamed Moynihan Train Hall.[247][248] In August 2017, a groundbreaking ceremony was held for the Moynihan Train Hall.[249] The train hall opened to the public on January 1, 2021.[250][251]

Penn Station South

West 31st St., including the New York Terminal Service Plant[252]
Capuchin Monastery of St John the Baptist, 31st St

Plans call for Penn Station South to be located on the block south of the current New York Penn Station at 31st Street and diagonally across Eighth Avenue from the post office, on land which is currently privately held.[253] While the PANYNJ had been acquiring land for ARC along its route, acquisition south of the station has not begun.[8] It is likely the entire block would be razed and made available for highrise construction after completion of the station.[254] Plans call for seven tracks served by four platforms in what will be a terminal annex to the entire station complex.[7] In April 2011 Amtrak requested $50 million in federal funding for preliminary engineering and environmental analysis.[65][192]

In 2014, it was estimated that it would cost $404 million to purchase 35 properties in order to build a new terminal at the location.[255] Based on development guidelines from the New York City Planning Commission, it is estimated that at 2015 prices it would cost between $769 million and $1.3 billion to buy the block bounded to the north and south by 31st and 30th streets, and to the east and west by Seventh and Eighth avenues. Real estate prices are 2½ times higher now than they were in 2012 according to prominent real estate firm Cushman & Wakefield.[256][257]

Related projects

Other projects in the New York metropolitan area are planned as part of the NEC Next Generation High Speed Rail, including the northern and southern approaches to the Gateway Project.[258]

New Brunswick–Trenton high-speed upgrade

In May 2011, $450 million was dedicated to increase capacity on one of the NEC's busiest segments, a 24-mile (39 km) section between New Brunswick and Trenton, New Jersey. The planned six-year project will upgrade signals and electrical power systems, including catenary wires, to improve reliability, increase train speeds, and allow more frequent high-speed trains.[259][260][261] In July 2011, a bill passed by the House of Representatives threatened funding for the project and others announced at the same time,[262][263] but the money was released the following month.[264] The project, along with the purchase of new train sets, is expected to raise speeds on the segment to 186 mph (299 km/h).[264] In September 2012, Acela test trains hit 165 mph (266 km/h) over the segment.[265][266] The track work is one of several projects planned for the "New Jersey Speedway" section of the NEC, which include a new station at North Brunswick, the Mid-Line Loop (a flyover for reversing train direction), and the re-construction of County Yard, to be done in coordination with NJT.[267]

Harold Interlocking and Hutchinson River

Over 750 LIRR, NJT, and Amtrak trains travel through the Harold Interlocking every day, causing frequent conflicts and delays.[264] In May 2011, a $294.7 million federal grant was awarded to address congestion at the USA's busiest rail junction and part of the Sunnyside Yard in Queens. The work will allow for a dedicated track to the New York Connecting Railroad right of way for Amtrak trains arriving from or bound for New England, thus avoiding NJT and LIRR traffic.[268][269] A new flying junction will allow Amtrak trains to travel through the interlocking separately from LIRR and NJ Transit trains on their way to Sunnyside.[264] Financing for the project was jeopardized when the House of Representatives voted in July 2011 to divert the money to unrelated projects,[263] but funds were later obligated so that work on the project could begin in 2012.[264] Some of the interlocking improvement projects are complete as of early 2023, while several other projects are projected for completion by late 2025.[270]

Amtrak applied in 2011 for $15 million for the environmental impact studies and preliminary engineering design to examine replacement options for the more than 100-year-old, low-level movable Pelham Bay Bridge over the Hutchinson River in the Bronx. The goal is for a new bridge to support expanded service and speeds up to 110 mph (177 km/h).[192] In August 2022, the FRA awarded a $4.5 million grant to Amtrak for the bridge replacement project.[271] In June 2023, Amtrak applied for additional FRA grants to support multiple improvement projects in the Northeast Corridor, including additional work on the Pelham Bay Bridge project.[272][273]

Subway service

While not part of the Gateway Project, Amtrak's announcement included a proposal to extend the Metropolitan Transportation Authority (MTA) 7 Subway Extension three blocks east to New York Penn Station from the current station at 11th Avenue and 34th Street. This would provide service to the Javits Convention Center and a one-seat ride to Grand Central Terminal, the city's other major train terminal on the East Side of Manhattan at 42nd Street.[7] Shortly before the introduction of Gateway, the New York City Economic Development Corporation voted to budget up to $250,000 for a feasibility study of a Hudson River tunnel for an extension to Secaucus Junction awarded to Parsons Brinckerhoff, a major engineering firm that had been working on the ARC tunnel.[274][275] In October 2011, NYC Mayor Michael Bloomberg reiterated his support for the NJ extension, estimated to cost around $10 billion and take ten years to complete, indicating that he would give approval by the end of his third term in 2013. Environmental-impact studies and a full business plan are required before the proposal proceeds.[276] It was likely that the two projects—Gateway and the subway extension—would have been in competition for funding.[277]

In April 2012, citing budget considerations, the director of the MTA effectively scuttled the project and said that it was doubtful the extension would be built in the foreseeable future, suggesting that the Gateway Project was a much more likely solution to congestion at Hudson River crossings.[278] The report was released in April 2013.[279][280] In a November 2013 Daily News opinion article, the president of the Real Estate Board of New York and the chairman of Edison Properties called for the line to be extended to Secaucus in tunnels to be shared with the Gateway Project.[281] In November 2013, the New Jersey Assembly passed a Resolution 168[282] supporting the extension of the line to Hoboken and Secaucus.[283]

See also

Notes

References

  1. ^ أ ب ت Porcari, John D. (يناير 12, 2017). "Gateway Program Overview and Update" (PDF). Gateway Program Development Corporation. p. 21. Archived (PDF) from the original on يناير 3, 2018. Retrieved يناير 1, 2018.
  2. ^ أ ب "Sandy-damaged tunnels could cause Amtrak nightmare". AP News. أكتوبر 2, 2014. Archived from the original on مايو 7, 2018. Retrieved مايو 7, 2018.
  3. ^ Gurley, Gabrielle (يناير 22, 2018). "Gateway To Nowhere on the Hudson". The American Prospect. Archived from the original on أكتوبر 16, 2022. Retrieved سبتمبر 12, 2018.
  4. ^ أ ب ت Bazeley, Alex (يوليو 6, 2017). "The Hudson Tunnel Project is expected to cost $12.9 billion". am New York. Archived from the original on مايو 7, 2018. Retrieved مايو 7, 2018.
  5. ^ Rouse, Karen (فبراير 8, 2011). "Amtrak president details Gateway Project at Rutgers lecture". Bergen Record. Retrieved فبراير 9, 2011.
  6. ^ أ ب Frassinelli, Mike (فبراير 6, 2011). "N.J. senators, Amtrak official to announce new commuter train tunnel project across the Hudson". The Star-Ledger. Archived from the original on فبراير 7, 2011. Retrieved فبراير 7, 2011.
  7. ^ أ ب ت ث ج ح خ د ذ ر ز س ش "Gateway Project" (PDF). Amtrak. فبراير 2011. Archived from the original (PDF) on مايو 17, 2013. Retrieved فبراير 7, 2011.
  8. ^ أ ب McGeehan, Patrick (فبراير 7, 2011). "With One Plan for a Hudson Tunnel Dead, Senators Offer Another Option". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 9, 2011.
  9. ^ "Lautenberg, Menendez Join Amtrak to Announce New Trans-Hudson Gateway Tunnel Project" (Press release). Lautenberg/US Senate press release. فبراير 7, 2011. Archived from the original on يوليو 21, 2011. Retrieved فبراير 21, 2011.
  10. ^ أ ب Frassinelli, Mike (فبراير 8, 2011). "Gov. Christie says new Gateway tunnel plan addresses his ARC project cost concerns". The Star-Ledger. Archived from the original on فبراير 10, 2011. Retrieved فبراير 9, 2011.
  11. ^ أ ب Caruso, Lisa (فبراير 7, 2011). "Amtrak Proposes $13.5 Billion New Jersey Rail Project". The Washington Post. Archived from the original on يونيو 28, 2011. Retrieved فبراير 16, 2011.
  12. ^ أ ب "Portal Bridge Capacity Enhancement". Amtrak, New Jersey Transit, U.S Department of Transportation. Archived from the original on فبراير 8, 2011. Retrieved فبراير 8, 2011.
  13. ^ أ ب ت ث Belsen, Ken (ديسمبر 31, 2008). "Approval Given for New Jersey Rail Bridges". The New York Times. ISSN 0362-4331. Archived from the original on أبريل 10, 2009. Retrieved فبراير 8, 2011.
  14. ^ Frassinelli, Mike (يناير 28, 2010). "NJ Transit announces $38.5M for Portal Bridge project, names executive director". The Star-Ledger. Archived from the original on يونيو 5, 2011. Retrieved فبراير 8, 2011.
  15. ^ أ ب Whiten, Jon (فبراير 8, 2010). "Advocates Want Bike/Ped Path as Part of Portal Bridge Project". Jersey City Independent. Archived from the original on يوليو 11, 2011. Retrieved فبراير 8, 2011.
  16. ^ "TIGER grant provides final piece of the Moynihan Station funding puzzle". United States Department of Transportation. أكتوبر 19, 2010. Archived from the original on نوفمبر 24, 2010. Retrieved فبراير 9, 2011.
  17. ^ Bagli, Charles V. (أكتوبر 18, 2010). "A Ceremonial Start for Moynihan Station". The New York Times. ISSN 0362-4331. Archived from the original on يوليو 14, 2011. Retrieved فبراير 9, 2011.
  18. ^ "The American Recovery and Reinvestment Act" (PDF). Njtransit.com. Archived from the original (PDF) on فبراير 6, 2015. Retrieved مايو 7, 2015.
  19. ^ "Written Testimony of Joan McDonald" (PDF). يونيو 7, 2013. Archived from the original (PDF) on سبتمبر 19, 2014. Retrieved ديسمبر 11, 2013.
  20. ^ "Transportation Investment Generating Economic Recovery (TIGER)". NY DOT. فبراير 6, 2015. Archived from the original on فبراير 6, 2015. Retrieved أكتوبر 26, 2017.
  21. ^ Tangel, Andrew (فبراير 1, 2015). "Work on New Hudson Train Tunnels Chugs Along". The Wall Street Journal. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 4, 2015.
  22. ^ Prout, H.G. (سبتمبر 14, 1902). "The Pennsylvania's Great Hudson River Tunnel". The New York Times. ISSN 0362-4331. Retrieved فبراير 16, 2011.
  23. ^ أ ب ت قالب:Cite Cudahy-Hudson
  24. ^ "Newark Adopts Plans for New Rail Station; How Newark Railroad Station Will Look". The New York Times. مايو 14, 1931. ISSN 0362-4331. Archived from the original on نوفمبر 6, 2012. Retrieved فبراير 21, 2011.
  25. ^ "Newark Dedicates its New Terminal; Railroad Station, Centre Link in $42,000,000 Project, Is Opened to the Public". The New York Times. مارس 24, 1935. ISSN 0362-4331. Archived from the original on يوليو 23, 2018. Retrieved فبراير 21, 2011.
  26. ^ "New Station Open for Hudson Tubes". The New York Times. يونيو 20, 1937. p. 1. ISSN 0362-4331. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 18, 2011.
  27. ^ Karnoutsos, Carmela; Shalhoub, Patrick (2007). "Exchange Place". Jersey City Past and Present. New Jersey City University. Archived from the original on أغسطس 14, 2004. Retrieved فبراير 16, 2011.
  28. ^ أ ب "Penn Station". New York Architecture Images – gone. nyc-architecture.com. Archived from the original on يونيو 4, 2011. Retrieved فبراير 18, 2011.
  29. ^ French, Kenneth (2002). Images of America: Railroads of Hoboken and Jersey City. USA: Arcadia Publishing. p. 30. ISBN 978-0-7385-0966-2. Archived from the original on أغسطس 1, 2015.
  30. ^ Pinkston, Elizabeth (2003). "A Brief History of Amtrak". U.S. Congressional Budget Office.
  31. ^ "A Brief History of Conrail". Consolidated Rail Corporation. 2003. Archived from the original on نوفمبر 21, 2010. Retrieved فبراير 16, 2011.
  32. ^ "Conrail, The Consolidated Rail Corporation". American-Rails.com. Archived from the original on مارس 17, 2011. Retrieved فبراير 16, 2011.
  33. ^ Pulley, Brett (فبراير 10, 1996). "Crash on New Jersey Transit;Agency Had Enviable Safety Record". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 16, 2011.
  34. ^ أ ب Hanley, Robert (سبتمبر 10, 1991). "Hoboken-Newark Rail Link Opens as Part of Multimillion-Dollar Expansion". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 20, 2011.
  35. ^ أ ب Chen, David W. (ديسمبر 8, 1996). "All Aboard for New York, if There's Parking Near the Train". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 16, 2011.
  36. ^ أ ب Hanley, Robert (مايو 1, 1991). "New Jersey to Add Trains to Midtown". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 16, 2022. Retrieved فبراير 16, 2011.
  37. ^ Sullivan, John (يونيو 2, 2002). "New Jersey's Amtrak Blues". The New York Times. ISSN 0362-4331. Archived from the original on فبراير 1, 2016. Retrieved فبراير 27, 2011.
  38. ^ Request for Information for Hudson Tunnel Project Archived يونيو 2, 2019 at the Wayback Machine. Amtrak Northeast Corridor. August 10, 2017. Accessed February 10, 2019.
  39. ^ "By Way of Jersey" (PDF). The New York Times. سبتمبر 4, 1910. ISSN 0362-4331. Archived (PDF) from the original on يوليو 8, 2021. Retrieved فبراير 27, 2011.
  40. ^ Wright, George Cable (يناير 23, 1962). "2 States Agree on Hudson Tubes and Trade Center; New York and Jersey Settle on Bill to Permit Port Authority Operation" (PDF). The New York Times. ISSN 0362-4331. Retrieved مايو 1, 2017.
  41. ^ "PATH map". Port Authority of New York and New Jersey. Archived from the original on نوفمبر 21, 2019. Retrieved مارس 7, 2011.
  42. ^ Sullivan, Ronald (فبراير 5, 1971). "Cahill Asks New Rail Tunnel to Manhattan". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Archived from the original on أبريل 10, 2018. Retrieved أبريل 9, 2018.
  43. ^ Editorial (نوفمبر 17, 2007). "Time to Move on Hudson Tunnel". The New York Times. ISSN 0362-4331. Archived from the original on أبريل 9, 2018. Retrieved فبراير 27, 2011.
  44. ^ "Transit Friendly Development". Voorhees Transportation Center/Rutgers University. مايو 2009. Archived from the original on يوليو 20, 2011. Retrieved مارس 7, 2011.
  45. ^ Port Authority of New York and New Jersey. "History Across the Hudson". The Star Ledger. Archived from the original on يوليو 14, 2011. Retrieved مارس 15, 2011.
  46. ^ Boburg, Shawn (ديسمبر 7, 2011). "Lawmakers urge PA to reduce bus delays". The Record. Archived from the original on يناير 15, 2013. Retrieved ديسمبر 14, 2011.
  47. ^ "Port Authority Bus Terminal History". Port Authority of New York and New Jersey. Archived from the original on يونيو 3, 2012. Retrieved مارس 7, 2011.
  48. ^ "New Report and Website Offer Speedier Bus Commute Across the Hudson River Report calls for Port Authority to prioritize bus trips for 100 million annual passengers". Tri-state Transportation Campaign. مايو 14, 2009. Archived from the original on نوفمبر 14, 2012. Retrieved أبريل 20, 2012.
  49. ^ Chernetz, Janna (أبريل 28, 2011). "NJ Transportation Funding Plan Would Shortchange Bus Riders". Mobilizing the Region. Archived from the original on سبتمبر 13, 2011. Retrieved أبريل 29, 2011.
  50. ^ Grossman, Andrew (أبريل 19, 2011). "Bus Terminal Hits Limit". The Wall Street Journal. Archived from the original on يونيو 11, 2015. Retrieved أبريل 29, 2011.
  51. ^ "Access to the Region's Core Major Investment Study Summary Report 2003" (PDF). arctunnel.com. 2003. Archived from the original (PDF) on أبريل 29, 2011. Retrieved مارس 6, 2011.
  52. ^ "Long Island Committee Meeting December 2015" (PDF). mta.info. Metropolitan Transportation Authority. ديسمبر 14, 2015. Archived from the original (PDF) on فبراير 25, 2016. Retrieved فبراير 17, 2016.
  53. ^ "LIRR full service begins Monday, 2/27, at Grand Central Madison; train schedules to change". ABC7 New York. فبراير 27, 2023. Retrieved فبراير 27, 2023.
  54. ^ Castillo, Alfonso A. (فبراير 26, 2023). "East Side Access completed, LIRR riders get full service to Grand Central Madison Monday". Newsday. Retrieved فبراير 27, 2023.
  55. ^ New Jersey Transit (October 2008). Newark, NJ. "Access to the Region's Core: Final Environmental Impact Study." Archived أغسطس 7, 2011 at the Wayback Machine Executive Summary.
  56. ^ Rassmussen, Ian (ديسمبر 15, 2010). "When an Environmental Impact Statement takes a lifetime". New Urban News. Archived from the original on يوليو 14, 2011. Retrieved مارس 7, 2012. The story of ARC began in 1995 with the start of a "Major Investment Study" that reviewed 137 alternative transportation improvements that would get commuters from central and northern New Jersey out of their cars, and into Manhattan faster, cheaper, and with less harm to the environment. After four years of study, the list was narrowed down to a few finalists in 1999. From 1999 to 2003, the feasibility of each of those plans (exactly where the tracks would be laid, and how they would connect to Penn Station) was studied, and the ultimate plan ironed out. From 2003 to 2009, the final plan — two new rail tunnels leading to a new lower level of Penn Station — was the subject of an Environmental Impact Statement (EIS).
  57. ^ أ ب ت Frassinelli, Mike (نوفمبر 8, 2010). "Hudson River tunnel project proposed by Amtrak, NJ Transit would take decades to complete". The Star Ledger. Archived from the original on يناير 19, 2011. Retrieved فبراير 27, 2011.
  58. ^ أ ب Fleisher, Liza; Grossman, Andrew (فبراير 8, 2011). "Amtrak's Plan For New Tunnel Gains Support". The Wall Street Journal. Archived from the original on يوليو 12, 2015. Retrieved فبراير 8, 2011.
  59. ^ أ ب "Amtrak, NJ Transit break off talks on reviving ARC Hudson River rail tunnel". The Star-Ledger. نوفمبر 12, 2010. Archived from the original on ديسمبر 19, 2010. Retrieved مارس 7, 2011.
  60. ^ McGeehan, Patrick (أكتوبر 7, 2010). "Christie Halts Train Tunnel, Citing Its Cost". The New York Times. Archived from the original on سبتمبر 3, 2011. Retrieved أكتوبر 8, 2010.
  61. ^ "Amtrak: no interest in Hudson tunnel". The Star-Ledger. نوفمبر 13, 2010. Archived from the original on يونيو 29, 2011. Retrieved مارس 13, 2011.
  62. ^ Higgs, Larry (فبراير 8, 2011). "Amtrak plans new tunnel under Hudson River". mycentraljersey.com. Archived from the original on يوليو 14, 2011. Retrieved فبراير 21, 2011.
  63. ^ Pillets, Jeff (فبراير 28, 2011). "State wants refund for $161.9M tunnel insurance". The Record. Archived from the original on سبتمبر 26, 2012. Retrieved مارس 14, 2011.
  64. ^ "Amtrak Seeks $1.3 billion for Gateway Project and Next-Generation High-Speed Rail on NEC". Amtrak. أبريل 4, 2011. Archived from the original on مايو 3, 2011. Retrieved أبريل 8, 2011.
  65. ^ أ ب ت ث Jackson, Herb (أبريل 4, 2011). "Amtrak seeking $1.3B for Hudson River tunnel planning, bridge replacement". The Record. Archived from the original on مايو 16, 2011. Retrieved أبريل 10, 2011.
  66. ^ Frassinelli, Mike (نوفمبر 18, 2011). "Engineering work to begin on Gateway train tunnel under Hudson River, Congress approves $15M for project". The Star-Ledger. Archived from the original on نوفمبر 20, 2011. Retrieved نوفمبر 22, 2011.
  67. ^ Boburg, Shawn (نوفمبر 2, 2011). "Senate OKs $15M in design funds for NJ-NY tunnel". The Record. Archived from the original on ديسمبر 3, 2013. Retrieved نوفمبر 2, 2011.
  68. ^ "U.S. Senate Approves Funding For NJ-NY Rail Tunnel Design". NJToday.com. نوفمبر 2, 2011. Archived from the original on يونيو 9, 2012. Retrieved نوفمبر 2, 2011.
  69. ^ "Senate Committee OKs $20 Million For Gateway Tunnel Project". CBS. أبريل 4, 2012. Archived from the original on يوليو 20, 2012. Retrieved يوليو 20, 2012.
  70. ^ "Lautenberg, Menendez Announce $20 Million For Gateway Tunnel Project Approved In Senate Committee" (Press release). Senate.gov. أبريل 19, 2012. Archived from the original on مايو 9, 2012. Retrieved يوليو 23, 2012.
  71. ^ "Senate Appropriations Committee approves $20 million for Gateway Tunnel". Hudson Reporter. أبريل 20, 2012. Archived from the original on مايو 5, 2012. Retrieved يوليو 23, 2012.
  72. ^ أ ب Marritz, Ilya (سبتمبر 28, 2012). "Sen. Schumer: Fast Action Needed for New Amtrak Tunnel". Transportation Nation. Archived from the original on أكتوبر 1, 2012. Retrieved أكتوبر 3, 2012.
  73. ^ Rouse, Karen (ديسمبر 6, 2012). "Amtrak asks Congress for emergency funding for flood protection". The Record. Archived from the original on ديسمبر 13, 2013. Retrieved نوفمبر 12, 2012.
  74. ^ Goldmark, Alex (ديسمبر 13, 2012). "Amtrak asks for subsidies in wake of Hurricane Sandy". Transportation Nation. Archived from the original on مايو 25, 2013. Retrieved ديسمبر 15, 2012.
  75. ^ "Testimony of Joseph H. Boardman... Hearing "Superstorm Sandy: the Devastating Impact on the Nation's Largest Transportation Systems"" (PDF). Amtrak. ديسمبر 6, 2012. Archived (PDF) from the original on ديسمبر 18, 2013. Retrieved يناير 25, 2013.
  76. ^ "President Obama signs $50B Sandy relief bill". The Star-Ledger. Associated Press. يناير 29, 2013. Archived from the original on ديسمبر 16, 2013. Retrieved يناير 29, 2013.
  77. ^ "Construction begins to preserve possible pathway of new train tunnels into penn station new york" (PDF). Amtrak. سبتمبر 13, 2013. Archived (PDF) from the original on ديسمبر 3, 2013. Retrieved نوفمبر 11, 2013.
  78. ^ "Price for New York-New Jersey rail tunnel rises to $12.9B". ABC News (in الإنجليزية). يوليو 6, 2017. Archived from the original on يوليو 7, 2017. Retrieved يوليو 9, 2017.
  79. ^ أ ب ت ث ج ح خ "Draft Environmental Impact Statement (DEIS) Executive Summary" (PDF). hudsontunnelproject.com. Federal Railroad Administration, New Jersey Transit. يونيو 2017. Archived (PDF) from the original on ديسمبر 15, 2017. Retrieved يوليو 10, 2017.
  80. ^ Goldman, Henry; Young, Elise (أغسطس 27, 2021). "NYC Rail Tunnel Cost Up 6% to $12.3 Billion on Trump Delays". Bloomberg. Archived from the original on ديسمبر 2, 2021. Retrieved يوليو 6, 2022.
  81. ^ Short, Aaron (أغسطس 31, 2021). "Gateway Tunnel Budget Increases to $12.3B". Commercial Observer. Archived from the original on يوليو 6, 2022. Retrieved يوليو 6, 2022.
  82. ^ Woodhouse, Skylar (يناير 20, 2022). "NYC Gateway Tunnel Gets Set for Federal Funding as U.S. Raises Priority". Bloomberg. Archived from the original on أكتوبر 16, 2022. Retrieved يوليو 6, 2022.
  83. ^ McGeehan, Patrick (يوليو 5, 2022). "Hudson River Tunnel Project Moves Ahead as States Agree to Share Costs". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Archived from the original on يوليو 5, 2022. Retrieved يوليو 6, 2022.
  84. ^ Katzban, Nicholas (يوليو 6, 2022). "NY and NJ governors sign memorandum to split cost of Gateway tunnel project". NorthJersey.com. Archived from the original on يوليو 6, 2022. Retrieved يوليو 6, 2022.
  85. ^ أ ب Rubinstein, Dana (أغسطس 31, 2022). "Commuter Tunnel Under the Hudson Won't Be Finished Until 2035". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Archived from the original on أكتوبر 6, 2022. Retrieved أكتوبر 6, 2022.
  86. ^ "Gateway tunnel cost jumps to $16.1B and construction start pushed back". Crain's New York Business. سبتمبر 1, 2022. Archived from the original on أكتوبر 7, 2022. Retrieved أكتوبر 7, 2022.
  87. ^ Maag, Christopher (نوفمبر 12, 2015). "Officials: Corporation will oversee new Hudson rail tunnel; feds will split cost". NorthJersey.com. Archived from the original on مارس 23, 2017. Retrieved مارس 22, 2017.
  88. ^ Higgs, Larry (نوفمبر 12, 2015). "Feds agree to fund half of new Hudson rail tunnels, Booker says". NJ.com. Archived from the original on مارس 22, 2017. Retrieved مارس 22, 2017.
  89. ^ Fitzsimmons, Emma G. (نوفمبر 11, 2015). "Corporation to Oversee New Hudson Rail Tunnel, With U.S. and Amtrak Financing Half". The New York Times. ISSN 0362-4331. Archived from the original on أبريل 4, 2017. Retrieved مارس 22, 2017.
  90. ^ Maag, Christopher (نوفمبر 12, 2015). "Signs of progress emerge on Hudson rail tunnel plan, but concern persists on finding $20B to fund it". NorthJersey.com. Archived from the original on مارس 23, 2017. Retrieved مارس 22, 2017.
  91. ^ "Booker, Schumer Menendez, Amtrak Chair Announce Breakthroughs Achieved in Just-Passed Transportation Bill that Provides Clear Path to Federal Funding for Gateway Tunnel". www.booker.senate.gov. ديسمبر 7, 2015. Archived from the original on أبريل 8, 2016. Retrieved مارس 25, 2016.
  92. ^ Higgs, Larry (مارس 23, 2016). "New Hudson River rail tunnels take big step forward". NJ.com. Archived from the original on مايو 1, 2017. Retrieved مارس 22, 2017.
  93. ^ Graber, Henry (أبريل 4, 2016). "What One Really Expensive Tunnel Means to U.S. Train Travel The price tag of New York and New Jersey's Gateway Project includes much more than a construction bill". NewCity. Archived from the original on أبريل 16, 2016. Retrieved أبريل 4, 2016.
  94. ^ Higgs, Larry (يناير 12, 2017). "Group starts funding effort for new Hudson River tunnels". NJ.com. Archived from the original on مايو 10, 2017. Retrieved مارس 22, 2017.
  95. ^ "Notice of Special Public Meeting of the Gateway Program Development Corporation" (in الإنجليزية). Amtrak. Archived from the original on أكتوبر 19, 2017. Retrieved يوليو 9, 2017.
  96. ^ Davis, Jeff (يوليو 1, 2017). "USDOT Withdraws From Gateway Corporation". The Eno Center for Transportation. Archived from the original on أكتوبر 26, 2017. Retrieved أكتوبر 26, 2017.
  97. ^ Munoz, Daniel J. (أبريل 22, 2019). "Gateway project hits hurdle with NJ, NY calls for oversight". NJBIZ. Archived from the original on أبريل 22, 2019. Retrieved أبريل 1, 2019.
  98. ^ Vielkind, Jimmy; Berger, Paul (أبريل 19, 2019). "Gateway Rail Tunnel Project Hits Another Hurdle". WSJ. Archived from the original on أبريل 19, 2019. Retrieved أبريل 1, 2019.
  99. ^ Wanek-Libman, Mischa (يونيو 24, 2019). "Bi-state legislation passed to establish Gateway Development Commission". Mass Transit Magazine. Archived from the original on يونيو 24, 2019. Retrieved يونيو 24, 2019.
  100. ^ Fazelpoor, Matthew (مايو 6, 2022). "Kolluri tapped to run Gateway Development Commission". NJBIZ. Archived from the original on يوليو 5, 2022. Retrieved يوليو 6, 2022.
  101. ^ Hoogensen, Finn (مايو 7, 2022). "Hochul, Murphy nominate CEO for Gateway Development Commission". PIX11. Archived from the original on مايو 14, 2022. Retrieved يوليو 6, 2022.
  102. ^ أ ب Nessen, Stephen; Solomon, Nancy (يوليو 18, 2024). "Hudson River tunnel project CEO quits after being referenced in Norcross indictment". Gothamist. Retrieved يوليو 19, 2024.
  103. ^ McGeehan, Patrick (مايو 7, 2015). "Obama Administration Urges Fast Action on New Hudson River Rail Tunnels". The New York Times. ISSN 0362-4331. Archived from the original on مايو 19, 2015. Retrieved مايو 12, 2015.
  104. ^ Maag, Christopher (مايو 7, 2015). "Port Authority chairman pledges to back Amtrak's Hudson River tunnel project". The Record. Archived from the original on مايو 9, 2015. Retrieved مايو 7, 2015.
  105. ^ "TRENTON, N.J.: Taxpayer price tag for transportation projects is unclear – Business". CentreDaily.com. Retrieved سبتمبر 22, 2015.[dead link]
  106. ^ Higgs, Larry (سبتمبر 15, 2015). "Christie, Cuomo ask Obama for money to build new rail tunnel, pledge state funds". The Star-Ledger. Archived from the original on سبتمبر 18, 2015. Retrieved سبتمبر 16, 2015.
  107. ^ Fitzsimmons, Emma G. (سبتمبر 16, 2015). "Cuomo and Christie Say States Can Pay Half of Hudson Rail Tunnel Project". The New York Times. ISSN 0362-4331. Archived from the original on سبتمبر 18, 2015. Retrieved سبتمبر 16, 2015.
  108. ^ Tangle, Andrew (سبتمبر 15, 2015). "Christie, Cuomo Ask Obama to Split Hudson River Tunnel Costs". The Wall Street Journal. Archived from the original on سبتمبر 15, 2015. Retrieved سبتمبر 16, 2015.
  109. ^ Reitmeyer, John (مارس 20, 2017). "Trump Infrastructure Flip-Flop Could Put Gateway Tunnel Project in Peril". NJ Spotlight. Archived from the original on مارس 23, 2017. Retrieved مارس 22, 2017.
  110. ^ Salant, Jonathon D. (مايو 17, 2017). "Trump transportation chief calls Gateway tunnel 'absolute priority'". The Star-Ledger. Archived from the original on مايو 23, 2017. Retrieved مايو 18, 2017.
  111. ^ Salant, Jonathan D. (سبتمبر 15, 2017). "What House just did with spending on Gateway Tunnel for new rail lines to NYC". NJ.com. Archived from the original on أكتوبر 19, 2017. Retrieved أكتوبر 26, 2017.
  112. ^ أ ب Salant, Jonathan D. (سبتمبر 6, 2017). "Will House Republicans take away Sandy funds after helping Harvey victims?". NJ.com. Archived from the original on مارس 4, 2018. Retrieved مارس 4, 2018.
  113. ^ أ ب ت DeBonis, Mike; Dawsey, Josh (مارس 2, 2018). "Trump pushes Republicans to oppose crucial New York-New Jersey tunnel project". Washington Post (in الإنجليزية الأمريكية). ISSN 0190-8286. Archived from the original on مارس 4, 2018. Retrieved مارس 4, 2018.
  114. ^ Nash, James (ديسمبر 14, 2017). "NJ Transit says Hudson River rail tunnel fix will require 90 cent fare increase to New York". North Jersey. Archived from the original on ديسمبر 17, 2017. Retrieved ديسمبر 14, 2017.
  115. ^ Betz, Bradford (ديسمبر 31, 2017). "Trump pulls brakes on $13B Obama-backed rail-tunnel plan". Fox News. Archived from the original on ديسمبر 31, 2017. Retrieved ديسمبر 31, 2017.
  116. ^ Bredderman, Will (ديسمبر 29, 2017). "Trump administration kills Gateway tunnel deal". Crain's New York Business. Archived from the original on ديسمبر 31, 2017. Retrieved ديسمبر 31, 2017.
  117. ^ Hogan, Gynne; Linge, Mary Kay (مارس 3, 2018). "Dems fume over Trump's push to cut funds for Gateway project". New York Post (in الإنجليزية الأمريكية). Archived from the original on مارس 3, 2018. Retrieved مارس 4, 2018.
  118. ^ "House Amendment to the Senate Amendment to H.R.1625, Consolidated Appropriations Act, 2018". Republican Policy Committee. مارس 22, 2018. Archived from the original on مارس 26, 2018. Retrieved مارس 25, 2018.
  119. ^ أ ب Niquette, Mark; Wasson, Erik (مارس 21, 2018). "New York-New Jersey Rail Project Gets Some Money in Congress Deal". Bloomberg.com (in الإنجليزية). Archived from the original on أبريل 2, 2018. Retrieved مارس 28, 2018.
  120. ^ DeBonis, Mike; O'Keefe, Ed; Werner, Erica (مارس 22, 2018). "Here's what Congress is stuffing into its $1.3 trillion spending bill". The Washington Post (in الإنجليزية الأمريكية). ISSN 0190-8286. Archived from the original on مارس 10, 2021. Retrieved مارس 25, 2018.
  121. ^ Guse, Clayton (مارس 27, 2018). "A pair of crucial new Hudson River tunnels just took a major step forward". Time Out New York (in الإنجليزية). Archived from the original on مارس 28, 2018. Retrieved مارس 28, 2018.
  122. ^ Tate, Curtis (يونيو 15, 2018). "Will new state funding move the feds to chip in for Portal Bridge?". North Jersey (in الإنجليزية). Archived from the original on أكتوبر 16, 2022. Retrieved أغسطس 13, 2018.
  123. ^ Hutter, David (يونيو 13, 2018). "NJ Transit board approves $600M bond to replace Portal Bridge". NJBIZ. Archived from the original on أغسطس 24, 2018. Retrieved أغسطس 13, 2018.
  124. ^ Reitmeyer, John (يونيو 13, 2018). "Floating a $600 Million Bond Issue to Build New Portal Bridge". www.njspotlight.com. Archived from the original on يونيو 19, 2018. Retrieved أغسطس 13, 2018.
  125. ^ "N.Y., N.J. Lawmakers Scramble For Backup Plan After Trump 2020 Budget Cuts Money From Gateway Project Fund". CBS New York. مارس 12, 2019. Archived from the original on يونيو 24, 2019. Retrieved يونيو 24, 2019.
  126. ^ Higgs, Larry; Salant, Jonathan D. (مارس 5, 2020). "Trump administration deals another blow to Gateway Tunnel". nj (in الإنجليزية). Archived from the original on مايو 2, 2020. Retrieved مايو 5, 2020.
  127. ^ McGeehan, Patrick (فبراير 27, 2020). "More Pain for N.J. Commuters: Tunnel Repairs Could Cause Big Delays". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Archived from the original on مارس 4, 2020. Retrieved مايو 5, 2020.
  128. ^ Hickman, Matt (يناير 26, 2021). "Stalled by Trump, $12 billion Gateway tunnel project poised to receive funding under Biden". The Architect's Newspaper (in الإنجليزية الأمريكية). Archived from the original on يناير 26, 2021. Retrieved مارس 29, 2021.
  129. ^ Kaske, Michelle (يناير 25, 2021). "NYC's Hudson Rail Tunnel Likely to Get More Funds, Schumer Says". BNN Bloomberg. Archived from the original on فبراير 3, 2021. Retrieved مارس 29, 2021.
  130. ^ "NYC-NJ tunnel plan has 'sense of urgency,' Buttigieg says". Crain's New York Business (in الإنجليزية). مارس 26, 2021. Archived from the original on مارس 30, 2021. Retrieved مارس 29, 2021.
  131. ^ McGeehan, Patrick (مايو 28, 2021). "At Long Last, a New Rail Tunnel Under the Hudson River Can Be Built". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Archived from the original on مايو 28, 2021. Retrieved مايو 28, 2021.
  132. ^ Higgs, Larry (مايو 28, 2021). "Gateway project to build new Hudson River tunnels wins key federal approval". nj. Archived from the original on مايو 28, 2021. Retrieved مايو 28, 2021.
  133. ^ Porter, David (مايو 28, 2021). "$11 Billion New York-New Jersey Rail Tunnel Gets Key Federal Approval". NBC New York. Archived from the original on مايو 28, 2021. Retrieved مايو 28, 2021.
  134. ^ DeFeo, T.A. (نوفمبر 8, 2021). "Infrastructure bill includes billions for Northeast Corridor". The Center Square. Archived from the original on نوفمبر 13, 2021. Retrieved نوفمبر 13, 2021.
  135. ^ Katzban, Nicholas (ديسمبر 1, 2021). "Gateway Project clears final hurdle, but tunnel construction won't begin until 2023". NorthJersey.com. Archived from the original on يناير 22, 2022. Retrieved ديسمبر 2, 2021.
  136. ^ Higgs, Larry (ديسمبر 1, 2021). "Hudson River rail tunnel gets green light from the feds to start building it". nj. Archived from the original on أكتوبر 16, 2022. Retrieved ديسمبر 2, 2021.
  137. ^ Stoltz, Marsha A. (سبتمبر 2, 2022). "Hudson tunnel project will be delayed by three years and cost $2B more, commission says". NorthJersey.com. Archived from the original on أكتوبر 16, 2022. Retrieved أكتوبر 6, 2022.
  138. ^ Higgs, Larry (يوليو 5, 2022). "N.J., N.Y. sign funding agreement on Gateway rail tunnel, bridge. Tunnel work could begin in 2023". nj. Retrieved ديسمبر 30, 2022.
  139. ^ Westbrook, Elijah (يوليو 6, 2022). "Governors Kathy Hochul and Phil Murphy sign $14B funding agreement for Gateway Hudson Tunnel project". CBS News. Retrieved ديسمبر 30, 2022.
  140. ^ "New Jersey Turnpike Authority to help pay state's share of Gateway Tunnel project". Trains. ديسمبر 21, 2022. Retrieved ديسمبر 30, 2022.
  141. ^ Higgs, Larry (ديسمبر 20, 2022). "N.J. Turnpike agrees to pay billions to help fund the Gateway Tunnel". nj. Retrieved ديسمبر 30, 2022.
  142. ^ Sanderson, Bill (ديسمبر 29, 2022). "Hudson River rail tunnel construction in NYC starting in 2023 with $292M federal grant, Schumer says". New York Daily News. Retrieved ديسمبر 30, 2022.
  143. ^ Tillman, Rachel (يناير 30, 2023). "Biden announces 9 'mega' grants for infrastructure projects". Spectrum News NY1 New York City. Retrieved فبراير 1, 2023.
  144. ^ Brachfeld, Ben (يناير 31, 2023). "'We're going to get it done': Biden touts $300M investment in Gateway Tunnel project on visit to NYC". amNewYork. Retrieved فبراير 1, 2023.
  145. ^ McGeehan, Patrick (يوليو 6, 2023). "Hudson Tunnel Project to Get $6.9 Billion in Largest U.S. Transit Grant". The New York Times. ISSN 0362-4331. Retrieved أغسطس 24, 2023.
  146. ^ Brachfeld, Ben (يوليو 6, 2023). "Biden admin awards nearly $7B to Gateway Tunnel project, largest federal transit grant in US history". amNewYork. Retrieved أغسطس 24, 2023.
  147. ^ Bergeron, Tom (يونيو 12, 2024). "Time to dig: Gateway Tunnel project gets full-funding grant ($6.8B) from federal government". ROI-NJ. Retrieved يونيو 12, 2024.
  148. ^ McGeehan, Patrick (يونيو 11, 2024). "Gateway Tunnel Project Under Hudson River Gets Final Green Light". The New York Times. Retrieved يونيو 12, 2024.
  149. ^ Siff, Andrew (يوليو 8, 2024). "$16 billion Gateway Tunnel Project gets federal funding boost after years of delays". NBC New York. Retrieved يوليو 9, 2024.
  150. ^ "Gateway rail tunnel project: Officials announce $6.8B grant to fund long-delayed path between NYC, NJ". ABC7 New York. يوليو 8, 2024. Retrieved يوليو 9, 2024.
  151. ^ أ ب McGeehan, Patrick (نوفمبر 3, 2023). "New Phase of Gateway Tunnel Project in Hudson River to Begin". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Retrieved نوفمبر 7, 2023.
  152. ^ Wilson, Colleen (نوفمبر 3, 2023). "NJ share of Gateway tunnel project cost to drop, feds add $4B". Bergen Record. Retrieved نوفمبر 7, 2023.
  153. ^ "Hudson Tunnel Project Awaits Final Approval in NYC". Hudson Reporter. مايو 30, 2024. Retrieved يونيو 3, 2024.
  154. ^ Woodhouse, Skylar (مايو 14, 2024). "NYC Rail Project Heads for 'Point of No Return' Before Election". Bloomberg. Archived from the original on مايو 14, 2024. Retrieved نوفمبر 14, 2024.
  155. ^ Rahmanan, Anna (يوليو 11, 2024). "A new tunnel will soon connect New York and New Jersey". Time Out New York (in الإنجليزية الأمريكية). Retrieved يوليو 12, 2024.
  156. ^ "About the Commission – Gateway Program". Gateway Program. يونيو 20, 2019. Retrieved يوليو 12, 2023.
  157. ^ Higgs, Larry (يناير 14, 2025). "Ex-MTA CEO to head agency building $16B Gateway rail tunnel, sources say". nj. Retrieved يناير 16, 2025.
  158. ^ Fazelpoor, Matthew (يناير 14, 2025). "Former MTA head Prendergast tapped to lead GDC". NJBIZ. Retrieved يناير 16, 2025.
  159. ^ McGeehan, Patrick; Glanz, James (أغسطس 20, 2024). "Why Amtrak's System Keeps Breaking Down: It's 100 Years Old". The New York Times. Retrieved أغسطس 25, 2024.
  160. ^ أ ب "NJ Transit's Response to Shifting Travel Demand in the Aftermath of September 11, 2001" (PDF). Travel Trends. New Brunswick: The Alan M. Voorhees Transportation Center. 3. Fall 2006. Archived from the original (PDF) on يوليو 20, 2011. Retrieved مارس 8, 2011. NJ TRANSIT financed a new High Density Signal system in conjunction with the Kearny Connection, Montclair Connection and Secaucus Transfer projects that allowed the total number of NJ TRANSIT and Amtrak peak period trains operating in the heavily congested NewarkPSNY corridor to increase from 18 per hour to 23. The new signal system enabled NJ TRANSIT to substantially increase its share of peak hour trains, from 11 (of theprior capacity of 18) to 17 or 18, depending on the hour, of the 23 now available. (The "New Initiatives" agreement anticipated a capacity of 25 trains during the peak hour; however, NJ TRANSIT and Amtrak, through informal agreement, have limited the maximum number of hourly moves to 23 because of the continuing need to "reverse" trains out of New York back to New Jersey to make additional runs. These "reverse moves" cross the path of inbound trains and consume one or two precious peak slots per hour into New York.
  161. ^ "Rules and Regulation" (PDF). Federal Register. 74 (101): 25448. مايو 28, 2009. Archived (PDF) from the original on يوليو 21, 2011. Retrieved فبراير 14, 2011.
  162. ^ "The Harrison PATH Station". Daily Harrison. Archived from the original on فبراير 24, 2011. Retrieved فبراير 15, 2011.
  163. ^ "NEC INFRASTRUCTURE PROJECTS OF RELEVANCE TO NEW JERSEY" (PDF). ARP. يناير 2013. Archived (PDF) from the original on يناير 26, 2016. Retrieved يناير 19, 2016.
  164. ^ أ ب Baldwin, Zoe (يناير 8, 2009). "Feds Open "Portal" to Expansion of NJ Transit's Network". Mobilizing the Region. Archived from the original on سبتمبر 19, 2009. Retrieved فبراير 10, 2011.
  165. ^ "Code of Federal Regulations, Title 33, Volume 1". Code of Federal Regulations. U.S. Government Printing Office. يوليو 1, 2007. pp. 616–617. Archived from the original on يوليو 21, 2011. Retrieved سبتمبر 11, 2012.
  166. ^ McGeehan, Patrick (ديسمبر 11, 2018). "For 80,000 Commuters, One Nemesis: A 108-Year-Old Bridge". New York Times. Archived from the original on نوفمبر 25, 2022. Retrieved نوفمبر 29, 2024.
  167. ^ Israel, Daniel (مايو 21, 2021). "Gateway Project advances, Portal North Bridge included". Hudson Reporter. Archived from the original on يونيو 27, 2021.
  168. ^ "Other Gateway Program Projects". Gateway Development Commission. أغسطس 9, 2022. Archived from the original on يوليو 20, 2024. Retrieved نوفمبر 29, 2024.
  169. ^ "Breaking ground for new Portal North Bridge in New Jersey". WABC-TV. أغسطس 1, 2022. Archived from the original on أغسطس 9, 2022. Retrieved أغسطس 6, 2022.
  170. ^ Johnson, Anthony (مايو 13, 2024). "Halfway done! Amtrak, NJ Transit announce new Portal North Bridge, on time and on budget". ABC7 New York. Retrieved مايو 14, 2024.
  171. ^ Caloway, Nick (نوفمبر 26, 2024). "Key milestone reached for new Portal North Bridge". CBS New York. Archived from the original on نوفمبر 27, 2024. Retrieved نوفمبر 29, 2024.
  172. ^ "High-Speed Intercity Passenger Rail (HSIPR) Program" (PDF). gov. Archived from the original (PDF) on يناير 5, 2011. Retrieved فبراير 10, 2011.
  173. ^ Copeland, Denise (يونيو 1, 2010). "Senator Lautenberg lends his support to bike and pedestrian access on the new Portal Bridge over the Hackensack". The Star-Ledger. Archived from the original on يوليو 14, 2011. Retrieved فبراير 19, 2011.
  174. ^ Maag, Christopher. "NJ Transit gets $16M grant for rail bridge replacement". NorthJersey.com. Retrieved أكتوبر 27, 2015.
  175. ^ Higgs, Larry; Salant, Jonathan D. (أكتوبر 27, 2015). "$16M federal grant will help replace Portal Bridge". The Star-Ledger. Archived from the original on أكتوبر 16, 2022. Retrieved أكتوبر 27, 2015.
  176. ^ "AECOM JV Bags US$18 Mln Contract For New Jersey's Portal Bridge Replacement Project – Quick Facts". RTT News. يناير 5, 2010. Archived from the original on يوليو 15, 2011. Retrieved يناير 11, 2010.
  177. ^ Racioppi, Dustin (يونيو 20, 2020). "Portal Bridge clears major hurdle and likely to get funding for replacement, Murphy says". northjersey.com (in الإنجليزية الأمريكية). North Jersey Media Group. Archived from the original on أغسطس 5, 2021. Retrieved يونيو 27, 2021.
  178. ^ "ARC Access to the Region's Core". New Jersey Transit. Archived from the original on فبراير 2, 2011. Retrieved فبراير 16, 2011.
  179. ^ Bowen, Douglas John (يونيو 19, 2013). "Secaucus Loop idea revived, tied to Gateway Tunnel". Railway Age. Archived from the original on أكتوبر 16, 2022. Retrieved نوفمبر 24, 2013.
  180. ^ Rouse, Karen (أبريل 24, 2012). "Amtrak's Gateway Proposal includes "Bergen Loop" to NYV". The Record. Archived from the original on أبريل 28, 2012. Retrieved أبريل 30, 2012.
  181. ^ "Gateway Tunnel Could Bring Direct Train Service from North Jersey to NYC". NJ Spotlight News. أبريل 26, 2012. Retrieved يناير 26, 2023.
  182. ^ Rife, Judy (أغسطس 31, 2014). "MTA urged to back Amtrak project 1-seat trip for Port riders to Midtown seen". Times Herald-Record. Archived from the original on سبتمبر 6, 2014. Retrieved سبتمبر 3, 2014.
  183. ^ Maag, Christopher (مارس 25, 2016). "Port Authority rail tunnel plan includes direct ride for North Jersey commuters". The Record. Archived from the original on مارس 25, 2016. Retrieved يوليو 26, 2016.
  184. ^ أ ب ت "Hudson Tunnel Project Draft Environmental Impact Study Chapter 5B Transportation Services" (PDF). hudsontunnelproject.com. Federal Railroad Administration, New Jersey Transit. يونيو 2017. Archived (PDF) from the original on سبتمبر 7, 2017. Retrieved يوليو 10, 2017.
  185. ^ أ ب "Amtrak Fact Sheet, Fiscal Year 2017, State of New Jersey" (PDF). Amtrak. 2017. p. 3. Archived (PDF) from the original on فبراير 6, 2021. Retrieved يناير 1, 2018.
  186. ^ "Amtrak Tunnels Flooded During Sandy To Reopen Friday". CBS New York. نوفمبر 7, 2012. Archived from the original on مايو 8, 2018. Retrieved مايو 7, 2018.
  187. ^ أ ب "Hudson Tunnel Project Draft Environmental Impact Statement (DEIS) Chapter 1 Purpose and Need" (PDF). hudsontunnelproject.com. يونيو 2017. Archived (PDF) from the original on يوليو 30, 2017. Retrieved يوليو 10, 2017.
  188. ^ Rubinstein, Dana (مايو 5, 2014). "Clock ticking on Hudson crossings, Amtrak warns". Capital. Archived from the original on مايو 10, 2014. Retrieved مايو 20, 2014.
  189. ^ Wanek-Libman, Mischa (يوليو 23, 2019). "How bad are delays caused by North River Tunnel and Portal Bridge? 2,000 lost hours bad". www.MassTransitMag.com (in الإنجليزية). Archived from the original on يوليو 26, 2019. Retrieved يوليو 26, 2019.
  190. ^ Barbara, Philip (أبريل 26, 2009). "Planned Hudson River rail tunnel isn't perfect, but it's good". The Star-Ledger. Archived from the original on يوليو 14, 2011. Retrieved مارس 6, 2011. One previous ARC design had a new NJ Transit station below Penn Station, which would enable all train platforms to be under one roof. But geologists found softer rock formations from an ancient stream bed that would not provide the necessary structural integrity required of new construction.....But planners found they could not repeat in a built-up city what the Pennsylvania Railroad did when it built the existing tunnel 100 years ago by digging a wide trench through the west side of Manhattan. The only solution was to dig deep – low enough to avoid the historic 90-foot-deep shoreline bulkhead and the New York Subway No. 7 line's extension. From that depth and in a short distance, trains can't reliably rise to make it into Penn Station. After repeated review, it was concluded a spur from the new tunnel was impossible.
  191. ^ "New York Property Information". Access to the Region's Core. PANYNJ/NJT. 2011. Archived from the original on مارس 3, 2011. Retrieved مارس 6, 2011.
  192. ^ أ ب ت "Amtrak Seeks $1.3 billion for Gateway Project and Next-Generation High-Speed Rail on NEC". Amtrak. أبريل 4, 2011. Archived from the original on مايو 3, 2011. Retrieved أبريل 8, 2011.
  193. ^ "Environmental Impact Statement (EIS) for the Hudson Tunnel Project in Hudson County, New Jersey and New York County, New York". Federal Railroad Administration. مايو 2, 2016. Archived from the original on مايو 12, 2016. Retrieved مايو 23, 2016.  هذا المقال يضم نصاً من هذا المصدر، الذي هو مشاع.
  194. ^ Simko-Bednarski, Evan (فبراير 16, 2024). "Gateway commission awards first contract in Hudson River tunnel project". New York Daily News. Retrieved فبراير 20, 2024.
  195. ^ Wilson, Colleen (فبراير 16, 2024). "Hudson riverbed to be stabilized for Gateway rail tunnel". Bergen Record. Retrieved فبراير 20, 2024.
  196. ^ "Officials sign off on $6.88 billion grant for Gateway Tunnel". Trains. يوليو 9, 2024. Retrieved يوليو 9, 2024.
  197. ^ "New Jersey Breaks Ground on Nation's Largest Transit Project" (Press release). New Jersey Transit. يونيو 8, 2009. Archived from the original on يونيو 27, 2010. Retrieved فبراير 13, 2010.
  198. ^ Wilshe, Brett (أكتوبر 31, 2010). "With ARC tunnel scrapped, NJ Transit officials wonder what to do with $26.3 million worth of North Bergen property". The Jersey Journal. Archived from the original on فبراير 11, 2011. Retrieved فبراير 15, 2011.
  199. ^ "Skanska to Construct Rail Tunnel in New York for USD 52 M, Approximately SEK 380 M". مايو 18, 2010. Archived from the original on يوليو 8, 2011. Retrieved فبراير 16, 2011.
  200. ^ Finkelstein, Alex (مايو 18, 2010). "Skanska Constructing $258 Million Palisades Tunnel for New Jersey Transit". Archived from the original on سبتمبر 8, 2012. Retrieved فبراير 19, 2011.
  201. ^ Frassinelli, Mike (أكتوبر 16, 2012). "NJ Transit still paying price for canceled Hudson River rail tunnel". The Star-Ledger. Archived from the original on مارس 22, 2013. Retrieved مارس 30, 2013.
  202. ^ Higgs, Larry (يونيو 23, 2023). "Feds give $25M to build N.J. highway bridge that was started and canceled in 2010". nj. Retrieved سبتمبر 12, 2023.
  203. ^ McGeehan, Patrick (سبتمبر 11, 2023). "13 Years Later, Construction to Restart on Hudson River Rail Tunnel". The New York Times (in الإنجليزية الأمريكية). ISSN 0362-4331. Retrieved سبتمبر 12, 2023.
  204. ^ Leggate, James (سبتمبر 12, 2023). "Gateway Awards Contracts for Early Work on New Jersey Side of Hudson Rail Tunnel". Engineering News-Record. Retrieved سبتمبر 12, 2023.
  205. ^ Gainer, Alice (نوفمبر 30, 2023). "Roadway bridge construction for Hudson River tunnel begins in North Bergen, N.J." CBS New York. Retrieved فبراير 20, 2024.
  206. ^ Bagli, Charles V. (ديسمبر 21, 2009). "Rezoning Will Allow Railyard Project to Advance". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 20, 2011. Retrieved ديسمبر 22, 2009.
  207. ^ "MTA Finalizes Hudson Yards Deal". Metropolitan Transportation Authority. مايو 26, 2010. Archived from the original on يونيو 2, 2010. Retrieved مايو 31, 2010.
  208. ^ Sichert, Bill (مارس 5, 2013). "Amtrak to construct 'tunnel box' for Hudson River rail project to cross Manhattan development". The Star-Ledger. Archived from the original on سبتمبر 4, 2020. Retrieved مارس 9, 2013.
  209. ^ Samtani, Hiten (فبراير 26, 2013). "Related, Amtrak to construct rail tunnel between Manhattan and NJ". The Real Deal. Archived from the original on مارس 5, 2013. Retrieved مارس 9, 2013.
  210. ^ Cuozzo, Steve (فبراير 26, 2013). "Fed money keeps rail tunnel alive". The New York Post. Archived from the original on مارس 1, 2013. Retrieved مارس 9, 2013.
  211. ^ Magyar, Mark J. (أكتوبر 21, 2013). "NJ Faces Hefty Pricetag for Rail Tunnel, Transportation Projects". NJ Spotlight. Archived from the original on أكتوبر 23, 2013. Retrieved نوفمبر 24, 2013.
  212. ^ "Second Trans-Hudson Tunnel Gets Some Real Money". Transportation Nation. WNYC. مايو 30, 2013. Archived from the original on يوليو 5, 2013. Retrieved نوفمبر 26, 2013.
  213. ^ Hawkins, Andrew (مايو 30, 2013). "Hudson train tunnel project gets kickstart". Crain's. Archived from the original on أبريل 1, 2017. Retrieved يناير 27, 2014.
  214. ^ Martinez, Jose (نوفمبر 6, 2013). "West Side Construction Project May Bring New Rail Tunnel Pathways To …". NY1.com. Archived from the original on نوفمبر 6, 2013. Retrieved أكتوبر 26, 2017.
  215. ^ "Environmental Assessment for Construction of a Concrete Casing in the Hudson Yards, New York, New York". Federal Railroad Administration. مارس 2013. Archived from the original on ديسمبر 2, 2013. Retrieved نوفمبر 24, 2013.
  216. ^ "Contract awarded for New York rail tunnel". Construction Index. سبتمبر 7, 2013. Archived from the original on ديسمبر 3, 2013. Retrieved نوفمبر 26, 2013.
  217. ^ Higgs, Larry (سبتمبر 1, 2014). "Amtrak: New tunnels needed after Sandy damage". Asbury Park Press. Archived from the original on أكتوبر 16, 2022. Retrieved سبتمبر 1, 2014.
  218. ^ Maag, Christopher (سبتمبر 21, 2014). "Signs of life stir for rail tunnel under Hudson". The Record. Archived from the original on سبتمبر 22, 2014. Retrieved سبتمبر 22, 2014.
  219. ^ "11th Avenue Viaduct Over LIRR Yard West 30th to West 33rd Streets" (PDF). NYC DOT. Archived from the original (PDF) on يونيو 2, 2010. Retrieved سبتمبر 3, 2014.
  220. ^ "Rehabilitation of 11th Avenue Viaduct Over LIRR/Amtrak" (PDF). Mueser Rutledge Consulting Engineers. Archived from the original (PDF) on مايو 13, 2008. Retrieved سبتمبر 3, 2014.
  221. ^ "Part of Hudson Yards Tunnels Is Nearly Done. Now It Sits, Unused". The New York Times. يوليو 20, 2017. ISSN 0362-4331. Archived from the original on أغسطس 31, 2018. Retrieved أغسطس 30, 2018.
  222. ^ "Long Island Rail Road Committee Meeting – March 2019" (PDF). mta.info. Metropolitan Transportation Authority. مارس 25, 2019. p. 50. Archived from the original (PDF) on مايو 24, 2019. Retrieved أغسطس 15, 2019.
  223. ^ "Hudson Yard Right-of-Way Preservation Project" (in الإنجليزية). Amtrak. Archived from the original on أكتوبر 19, 2017. Retrieved يوليو 9, 2017.
  224. ^ Brosnan, Erica (نوفمبر 3, 2023). "Gateway Tunnel project work begins amid $3.8B in new funding". NY1 (in الإنجليزية). Retrieved نوفمبر 9, 2023.
  225. ^ Jaffee, Eric (ديسمبر 22, 2011). "Can Amtrak Afford Its New NYC Home?". Atlantic Monthly. Archived from the original on فبراير 12, 2012. Retrieved ديسمبر 28, 2011.
  226. ^ أ ب Editorial (فبراير 23, 2010). "Moynihan Station, Finally?". The New York Times. ISSN 0362-4331. Archived from the original on أكتوبر 27, 2017. Retrieved فبراير 9, 2011.
  227. ^ Grynbaum, Michael M. (أكتوبر 18, 2010). "The Joys and Woes of Penn Station at 100". The New York Times. ISSN 0362-4331. Archived from the original on سبتمبر 30, 2020. Retrieved فبراير 16, 2011.
  228. ^ Gould, Jessica (يوليو 24, 2013). "City Council Limits Lease on Madison Square Garden, Makes Way for a New Penn Station". WNYC. Archived from the original on ديسمبر 3, 2013. Retrieved نوفمبر 24, 2013.
  229. ^ Bagli, Charles V. (يوليو 25, 2013). "Madison Square Garden told to move". The New York Times. ISSN 0362-4331. Archived from the original on نوفمبر 13, 2013. Retrieved نوفمبر 24, 2013.
  230. ^ Smith, Stephen Jacob (أغسطس 13, 2013). "Vanity Project: Why Fancy Architecture Won't Save Penn Station". The New York Observer. Archived from the original on ديسمبر 2, 2013. Retrieved نوفمبر 24, 2013.
  231. ^ Blumenthal, Sidney (مارس 14, 1994). "To the Pennsylvania Station". The New York. Archived from the original on أكتوبر 21, 2012. Retrieved فبراير 19, 2011.
  232. ^ Lueck, Thomas J. (نوفمبر 11, 1999). "A $60 Million Step Forward In Rebuilding Penn Station". The New York Times. ISSN 0362-4331. Archived from the original on سبتمبر 25, 2015. Retrieved فبراير 9, 2011.
  233. ^ "No. 7 Subway Extension – Hudson Yards Rezoning and Development Program" (PDF). nyc.gov. Archived from the original (PDF) on مارس 4, 2016. Retrieved فبراير 9, 2011.
  234. ^ Castillo, Alfonso A. (فبراير 16, 2010). "First phase of Penn Station overhaul fully funded". Newsday. Archived from the original on فبراير 4, 2021. Retrieved ديسمبر 31, 2020.
  235. ^ Michaelson, Juliette (فبراير 16, 2010). "Moynihan Station Awarded Federal Grant" (PDF). Friends of Moynihan Station. Archived from the original (PDF) on يوليو 14, 2010. Retrieved فبراير 17, 2010.
  236. ^ Strunsky, Steve (مايو 10, 2012). "Multi-million dollar contract awarded for long-planned expansion of New York's Penn Station". NJ Advance. Archived from the original on ديسمبر 31, 2020. Retrieved ديسمبر 31, 2020.
  237. ^ "New York Penn Station expansion to finally see light of day". Trains. أكتوبر 18, 2010. Archived from the original on مارس 19, 2011. Retrieved أكتوبر 20, 2010.
  238. ^ "Work to begin on massive Penn Station expansion". Long Island Business News. Associated Press. مايو 9, 2012. Archived from the original on مايو 12, 2012. Retrieved مايو 9, 2012.
  239. ^ Bagli, Charles V. (أكتوبر 18, 2010). "A Ceremonial Start for Moynihan Station". The New York Times. ISSN 0362-4331. Archived from the original on يوليو 14, 2011. Retrieved فبراير 9, 2011.
  240. ^ "Work to begin on massive Penn Station expansion". Long Island Business News. Associated Press. مايو 9, 2012. Archived from the original on مايو 12, 2012. Retrieved مايو 9, 2012.
  241. ^ Boburg, Shawn (مايو 8, 2012). "New Amtrak station to relieve rush-hour crowds at Penn Station in first phase of project". The Record. Archived from the original on مايو 10, 2012. Retrieved مايو 14, 2012.
  242. ^ Brenzel, Kathryn (يونيو 15, 2017). "First phase of Moynihan Train Hall project opens on Eighth Ave". The Real Deal New York. Archived from the original on أبريل 19, 2021. Retrieved ديسمبر 31, 2020.
  243. ^ Martinez, Jose (يونيو 15, 2017). "New Penn Station Entrance Part of Bigger Plan to Revamp Rail Hub". Spectrum News NY1 | New York City. Archived from the original on أبريل 22, 2021. Retrieved ديسمبر 31, 2020.
  244. ^ Warerkar, Tanay (يونيو 15, 2017). "Penn Station's West End Concourse finally opens to the public". Curbed NY. Archived from the original on يونيو 15, 2017. Retrieved ديسمبر 31, 2020.
  245. ^ Bagli, Charles V.; Fitzsimmons, Emma G. (يناير 7, 2016). "Cuomo Lays Out Renovation Plan for Penn Station and Farley Post Office". The New York Times. ISSN 0362-4331. Archived from the original on مارس 16, 2016. Retrieved مايو 30, 2016.
  246. ^ "Penn Station Renovation – Moynihan – Empire State Station". The Real Deal New York. أبريل 22, 2016. Archived from the original on مايو 29, 2016. Retrieved مايو 30, 2016.
  247. ^ Tangel, Andrew; West, Melanie Grayce (يناير 8, 2016). "New Name for Revamped Penn Station Surprises Moynihan Officials, Sparks Debate". Wall Street Journal. ISSN 0099-9660. Archived from the original on مارس 6, 2019. Retrieved مارس 6, 2019.
  248. ^ Hardt, Bob (يناير 7, 2016). "NY1 ItCH: Let's Not Rename Moynihan Station". Spectrum News NY1 | New York City. Archived from the original on مارس 6, 2019. Retrieved مارس 6, 2019.
  249. ^ Nasa, Rahima; Blain, Glenn (أغسطس 17, 2017). "Cuomo touts $1.6B train hall project next to Penn Station". NY Daily News (in الإنجليزية). Archived from the original on سبتمبر 6, 2017. Retrieved سبتمبر 6, 2017.
  250. ^ Re, Justine (يناير 1, 2021). "Moynihan Train Hall Opens at Penn Station". www.ny1.com (in الإنجليزية). Archived from the original on يناير 1, 2021. Retrieved يناير 1, 2021.
  251. ^ "Moynihan Train Hall Finally Opens in Manhattan". NBC New York (in الإنجليزية الأمريكية). يناير 1, 2021. Archived from the original on ديسمبر 31, 2020. Retrieved ديسمبر 31, 2020.
  252. ^ "Pennsylvania Station, New York Terminal Service Plant, 250 West Thirty-first Street, New York, New York County, NY". HAER. Archived from the original on مايو 11, 2015. Retrieved نوفمبر 25, 2014. …constructed as an integral component of the original Pennsylvania Station complex and served as a power generation and control center for the station, its tracks and signal systems. the facade was designed by McKim Mead & White to complement the exterior of the Pennsylvania Station. While much of the original service equipment has been dismantled or abandoned, some of the original power distribution equipment is still in use...
  253. ^ Penn 2023 Envisioning a new Penn Station, the next Madison Square Garden, and the future of west Midtown. Regional Plan Association. October 17, 2013. Archived from the original. You must specify the date the archive was made using the |archivedate= parameter. http://www.rpa.org/library/pdf/RPA-MAS-Penn-2023.pdf. 
  254. ^ Colvin, Jill (فبراير 17, 2011). "Midtown block would likely get razed for Gateway plan". DNAinfo.com. Archived from the original on فبراير 27, 2011. Retrieved مارس 7, 2011.
  255. ^ Higgs, Larry (أكتوبر 7, 2014). "Why Amtrak would have to buy $400M in NYC real estate to build new Hudson tunnel". The Star-Ledger. Archived from the original on أكتوبر 9, 2014. Retrieved أكتوبر 7, 2014.
  256. ^ Maag, Christopher (يناير 17, 2015). "Hudson River train tunnel hinges on pricey plan". The Record. Archived from the original on مارس 16, 2017.
  257. ^ Maag, Christopher (يناير 19, 2015). "N.Y.C. shrine to saint complicates Amtrak station plan". The Record. Archived from the original on مارس 4, 2016.
  258. ^ "Critical Infrastructure Needs on the Northeast Corridor" (PDF). Northeast Corridor Infrastructure and Operations Advisory Commission. يناير 2013. Archived from the original (PDF) on مارس 4, 2016. Retrieved يناير 19, 2016.
  259. ^ Frassinelli, Mike (مايو 9, 2011). "Feds steer $450M to N.J. for high-speed rail". The Star Ledger. Archived from the original on فبراير 10, 2012. Retrieved مايو 13, 2011.
  260. ^ Thorbourne, Ken (مايو 9, 2011). "Amtrak to receive nearly $450 million in high speed rail funding". The Jersey Journal. Archived from the original on أكتوبر 18, 2012. Retrieved مايو 13, 2011.
  261. ^ McGeehan, Patrick (مايو 9, 2011). "Florida's rejected rail funds flow north". The New York Times. ISSN 0362-4331. Archived from the original on مارس 4, 2018. Retrieved مايو 13, 2011.
  262. ^ Frassinelli, Mike (يوليو 16, 2011). "House passes bill that would divert money from electrical upgrades on N.J. Northeast". The Star-Ledger. Archived from the original on سبتمبر 16, 2011. Retrieved يوليو 16, 2011.
  263. ^ أ ب "House Vote Jeopardizes Key Northeast Rail Projects". Back on Track: Northeast. The Business Alliance for Northeast Mobility. يوليو 20, 2011. Archived from the original on سبتمبر 30, 2011. Retrieved يوليو 21, 2011.
  264. ^ أ ب ت ث ج Schned, Dan (أغسطس 24, 2011). "U.S. DOT Obligates $745 Million to Northeast Corridor Rail Projects". America 2050. Archived from the original on فبراير 20, 2012. Retrieved نوفمبر 24, 2011.
  265. ^ Frassinelli, Mike (سبتمبر 25, 2012). "Amtrak train looks to break U.S. speed record in Northeast Corridor test". The Star-Ledger. Archived from the original on ديسمبر 19, 2012. Retrieved ديسمبر 17, 2012.
  266. ^ Sheehan, Rebecca (سبتمبر 26, 2013). "Amtrak tests of Acela express train at 165 mph will not affect commuters". New Jersey Newsroom. Archived from the original on ديسمبر 3, 2013. Retrieved نوفمبر 24, 2013.
  267. ^ Vantuono, William C (يونيو 11, 2013). "Amtrak sprints toward a higher speed future". Railway Age. Archived from the original on يناير 17, 2014. Retrieved يناير 19, 2014.
  268. ^ "Maloney Hails Federal Grant to Ease Amtrak Delays in NYC, Spur High-Speed Rail in NE Corridor – $294.7 Million Grant to Improve "Harold Interlocking", a Delay-Plagued Junction For Trains in the NE Corridor". Congresswoman Carolyn B. Maloney. مايو 9, 2011. Archived from the original on سبتمبر 28, 2011. Retrieved مايو 13, 2011.
  269. ^ Colvin, Jill (مايو 9, 2011). "New York Awarded $350 Million for High-Speed Rail Projects". DNAinfo.com. Archived from the original on مايو 13, 2011. Retrieved مايو 13, 2011.
  270. ^ Milestone Report; Network Expansion—Regional Investments. MTA. Archived from the original. You must specify the date the archive was made using the |archivedate= parameter. http://dsearch.mta.info/ibi_apps/WFServlet?IBIF_ex=capitaldashboard_live/milestone_report_pf.fex&AGENCY=G&CATEGORY=All&PHASE=All&TIMELINE=T3&SCHEDSTAT=TL&CATDES=All%20Categories. Retrieved on February 8, 2023. 
  271. ^ "Biden Administration, USDOT Announce Over $233 Million in Grants to Upgrade Intercity Passenger Rail Service". FRA. أغسطس 18, 2022.
  272. ^ Toll, Beth (يونيو 5, 2023). "Amtrak Applies for $7.3 Billion in Federal Grants to Advance Northeast Corridor Infrastructure Upgrades". Amtrak Media. Retrieved أغسطس 24, 2023.
  273. ^ "Amtrak applies for federal grants to expand services". Railway Gazette International. يونيو 7, 2023. Retrieved أغسطس 24, 2023.
  274. ^ Bernstein, Andrea (فبراير 4, 2011). "City finally puts $ behind subway to New Jersey". Transportation Nation. Archived from the original on فبراير 6, 2011. Retrieved فبراير 7, 2011.
  275. ^ New York City Economic Development Commission (فبراير 2, 2011). "No. 7 Line Extension to Secaucus Consultant Services" (PDF). scribd.com. Archived from the original on نوفمبر 6, 2012. Retrieved فبراير 7, 2011.
  276. ^ "N.Y. mayor Bloomberg supports extending No. 7 subway into N.J." The Star-Ledger. أكتوبر 26, 2011. Archived from the original on نوفمبر 28, 2011. Retrieved نوفمبر 22, 2011.
  277. ^ Higgs, Larry (نوفمبر 19, 2011). "Obama expected to OK $15M for tunnel project between Secaucus and New York – Amtrak tunnel vs. extended subway to Secaucus showdown likely". Asbury Park Press. Retrieved نوفمبر 23, 2011.
  278. ^ Haughney, Christine (أبريل 3, 2012). "MTA Chief rules out subway line to New Jersey". The New York Times. ISSN 0362-4331. Archived from the original on أغسطس 18, 2012. Retrieved أبريل 4, 2012.
  279. ^ Frasinelli, Mike (أبريل 10, 2013). "Plan to extend No. 7 subway from NYC to New Jersey could be back on track". The Star-Ledger. Archived from the original on ديسمبر 15, 2018. Retrieved أبريل 10, 2013.
  280. ^ Rouse, Karen (أبريل 10, 2013). "Report: Extending NY No. 7 subway line to Secaucus would accommodate commuter demand". The Record. Archived from the original on أبريل 13, 2013. Retrieved أبريل 10, 2013.
  281. ^ Gottesman, Jerry; Spinola, Steven (نوفمبر 4, 2013). "Let's extend the 7 train to Secaucus After the far West Side, the next stop on the 7 should be across the river". Daily News. Archived from the original on ديسمبر 1, 2020. Retrieved نوفمبر 4, 2013.
  282. ^ "AN ASSEMBLY RESOLUTION supporting the extension of the New York City IRT Flushing Line into the State of New Jersey" (PDF). ASSEMBLY RESOLUTION No. 168 STATE OF NEW JERSEY 215th LEGISLATURE. New Jersey Legislature. مايو 13, 2013. Archived from the original (PDF) on سبتمبر 19, 2020. Retrieved نوفمبر 26, 2013.
  283. ^ Brenzel, Kathryn (نوفمبر 26, 2013). "Committee green lights expansion of NYC subway to Hoboken". The Star-Ledger. Archived from the original on نوفمبر 5, 2018. Retrieved نوفمبر 26, 2013.

Further reading

External links

KML is not from Wikidata